Print Actual Production Costs (ticst0415m000)
Use this session to print a report with material costs, operation costs, subcontracting costs, and standard cost surcharges for the actual costing of production orders.
You can print:
- All costs by project/production order.
- All costs by main item in a specific period.
- All costs by a department in a specific period.
LN prints the actual costing data stored in the Job Shop Financial Transactions (ticst3500m000) session or the PCS Financial Transactions by Transaction Origin and Financial Trans. (tipcs3500m000) session.
Field Information
- Site
-
The site ID.
Note: Only visible if multisite functionality is active. - Selections
-
- Select Print Method
-
Specify how the costs are grouped on the report.
Allowed values
- Order
- Project (PCS), Order
- Project Peg, Order
- Department, Transaction Date
- Main Item, Transaction Date
- Selection Range
-
- Project (PCS)
-
If this check box is selected, chose the range of Projects (PCS) for which actual production costs are printed.
- Project
-
If this check box is selected, chose the range of Projects for which actual production costs are printed.
- Element
-
If this check box is selected, chose the range of Elements for which actual production costs are printed.
- Activity
-
If this check box is selected, chose the range of Activities for which actual production costs are printed.
- Production Order
-
If this check box is selected, chose the range of Production Orders for which actual production costs are printed.
- Costing Work Center
-
If this check box is selected, chose the range of Costing Work Centers for which actual production costs are printed.
- Transaction Date
-
If this check box is selected, chose the range of Transaction Dates for which actual production costs are printed.
- Main Item
-
If this check box is selected, you can specify a range of items for which actual production costs are printed.
- Settings
-
- Currency for details
-
Select in which currency the costs must be printed.
Note:- If the Currency System of your company is Single or Dependent, this field is enabled.
- If the Currency System of your company is Independent, this field is disabled and displays Reference.
Allowed values
- Reference
- Calculation Office
-
The currency of the calculation office
- Department or Warehouse
- Currency Total
-
Any other currency.
- Currency for totals
-
LN prints the cost amounts in this currency.
Note:- In the Currency for details field you can select in which currency the costs must be printed.
- If you select Currency Total in the Currency for details field, you can enter a currency in this field.
- Exchange Rate Type
- Detail Level
-
- Group by
-
- Detail Level
-
Select how the actual costs are grouped:
Allowed values
- By Cost Type
- By Cost Component
- By Transaction Date
- Options
-
- Print Closed Orders Only
-
If this check box is selected, only orders with the Closed status are printed.
- Exclude Already Printed Orders
-
If this check box is selected, LN only prints orders that were not printed before.
- Include Customer Owned
-
If this check box is selected, customer owned materials are included in the report.
-
- Material Costs
-
If this check box is selected, LN prints material costs in the report.
- Subcontracting Costs
-
If this check box is selected, LN prints subcontracting costs in the report.
- Operation Costs
-
If this check box is selected, LN prints operation costs in the report.
- Surcharges
-
If this check box is selected, LN prints the surcharges in the report.