Alternative Estimated Materials (ticst0150m000)

Use this session to view the use-up materials and alternative materials linked to the estimated materials.

You cannot modify the data in this session.

To modify the alternatives defined for an estimated material, execute the following steps:

  1. Change the alternative materials linked to the lines of the bill of material (BOM). For detailed information, refer to Defining alternative materials.
  2. Then, run the Generate Alternatives for Estimated Materials (ticst0216m000) session.

Field Information

Production Order

production order

Position

The component's position number in the Estimated Materials (ticst0101m000) sesion.

Site

The site ID.

Alternative

Identification of the alternative-material record.

Alternative Priority

The alternative priority determines which of the alternatives LN will select first.

Allowed values

  • Use up

    This is an outdated material ( use-up material) that must be used up first.
  • Original

    The standard item.
  • 1

    The alternative that will be selected if the inventory of the standard material (and the use-up material, if any) is insufficient.
  • 2

    The alternative that will be selected if the inventory of the standard material and the first alternative material (and the use-up material, if any) is insufficient.
  • 3, 4, 5, ...

    Lower priority alternative materials.
  • 9

    The lowest priority alternative material.

Alternative Item

The alternative material.