Effective Cost Component Structure (ticpr0112m000)
Use this session to display the list of cost components for the selected item.
Field Information
- Cost Component
- Usage
-
Specify cost component usage.
Allowed values
- Detail
-
Used to collect costs defined for the specified cost component.
Optional for a valid cost component scheme.
- Collect
-
Used to define costs or rates that are not specifically defined in the cost component scheme. None-specific costs are collected on the related collect cost component.
Note: A valid cost component scheme must have one cost component of the type Collect with the General Costs. - Aggregated
-
Used to aggregate detail and collect cost components by type: materials, operations, surcharges and general. Each cost component scheme must have an aggregate cost component for each of the types.
Note: A valid cost component scheme must have aggregated cost components specified for all four component types.
- Cost Component Type
-
Specify the type of costs linked to the cost component.
Allowed values
- Operation Costs
-
You can link cost components of this cost type to:
- Subcontracting items
- Operation-rate codes
- Material Costs
-
You can link cost components of this cost type to:
- Standard items
- Customized items
- Calculation parts
- Project items
- Service items
- Surcharge
-
Unspecified additional costs incurred during the manufacturing process.
- Obsolete
-
You can use this cost type to define cost incurred, for example, when you transfer goods from one work center to another.
- General Costs
-
You can link cost components of this cost type to:
- Cost items
Examples of general costs are: freight costs, purchase costs, traveling expenses, and so on.
- Not Applicable
-
You must use this value for cost components that are used in Service and in Project .