Job Shop Bill of Material Control (tibom5100m000)
Use this session to manage templates that specify which attributes of a PLM-BOM are controlled by PLM or LN.
- The Engineering Revisions check box is selected in the Implemented Software Components (tccom0100s000) session.
- The Originating App field is set to PLM (Internal) or PLM (external) in the Item Base Data Parameters (tcibd9199m000) session.
-
If no template is defined, the PLM-BOM is defined by the attributes as sent by PLM and no validation is possible. Without validation, it is not possible to generate a job shop bill of material.
- Some attributes can only be controlled by PLM or controlled by LN.
Field Information
- Effective Date
-
The date the bill of material control template becomes effective.
- Settings
-
- Originating App
- Indicates the application used to view the domains.
- Allowed Manual Changes to Job Shop BOM
-
- Manual Add Revision
- If this check box is selected, the application allows the revision to be added manually.
- Modify PLM Controlled Fields
- If this check box is selected, the application allows us to modify PLM controlled fields.
- Manually Add/Delete Materia Line
- If this check box is selected, the application allows us to
manually add/delete the material line. Note: If this check box is selected, the application allows us to manually add/delete the material line.
- Manually Add/Delete Alternative Material
- If this check box is selected, the application allows us to
manually add/delete the alternative Material. Note: This check box is enabled if the Manually Add/Delete Materia Line checkbox is enabled.
- Manually Add/Delete Reference Designator
- If this check box is selected, the application allows us to
manually add/delete the reference designator.Note: This check box is enabled if the Manually Add/Delete Materia Line checkbox is enabled.
- Received Revision Handling
-
- Automatic Processing
- If this check box is selected, the application processes the revision automatically.
- Automatic Approving
- If this check box is selected, the application approves the
revision automatically. Note: This check box is enabled if the Automatic Processing checkbox is enabled.
- Print Process Report
- If this check box is selected, the application prints the
process report.Note: This check box is enabled if the Automatic Processing checkbox is enabled.
- Site
-
The site where the job shop bill of material is:
Allowed values
- Controlled by PLM
- Source Model
-
The job shop bill of material (BOM) is:
Allowed values
- Controlled by PLM
- Source Revision
-
The product revision is:
Allowed values
- Controlled by PLM
- Product
-
The product is:
Allowed values
- Controlled by PLM
- Routing
-
The routing used for the specified job shop bill of material is:
Allowed values
- Controlled by LN
- Controlled by PLM
- BOM Quantity
-
The BOM quantity of the specified job shop bill of material is:
Allowed values
- Controlled by PLM
- Use for Planning
-
Specifies if the selected job shop bill of material is used for planning purposes.
Use in planning is:
Allowed values
- Controlled by LN
- Use for Costing
-
Specifies if the selected job shop bill of material is used for costing purposes.
Use in costing is:
Allowed values
- Controlled by LN
- Effective Date
-
The date the job shop bill of material becomes effective.
The effective date is:
Allowed values
- Controlled by PLM
- Expiry Date
-
The date after which the job shop of material is no longer effective.
The expiry date is:
Allowed values
- Controlled by PLM
- BOM Text
-
The presence of additional bill of material text is:
Allowed values
- Controlled by LN
- Controlled by PLM
- Position
-
The position in the production queue is:
Allowed values
- Controlled by PLM
- Item
-
The item specifics are:
Allowed values
- Controlled by PLM
- Warehouse
-
The warehouse from which the materials for production are taken is:
Allowed values
- Controlled by LN
- Controlled by PLM
- Lot Selection
-
The lot selection is:
Allowed values
- Controlled by LN
- Controlled by PLM
- Net Quantity
-
The net quantity is:
Allowed values
- Controlled by LN
- Controlled by PLM
- Scrap Percentage
-
The scrap percentage is:
Allowed values
- Controlled by LN
- Controlled by PLM
- Scrap Quantity
-
The scrap quantity is:
Allowed values
- Controlled by LN
- Controlled by PLM
- Size Unit
-
The unit of measurement for length and width is:
Allowed values
- Controlled by LN
- Controlled by PLM
- Length
-
The length of the material is:
Allowed values
- Controlled by LN
- Controlled by PLM
- Width
-
The width of the material is:
Allowed values
- Controlled by LN
- Controlled by PLM
- Number of Units
-
The required quantity of the material, expressed as the number of units of specified length and width is:
Allowed values
- Controlled by LN
- Controlled by PLM
- Operation
-
The operation is:
Allowed values
- Controlled by LN
- Controlled by PLM
- M-R Relations Present
-
The presence of material-routing relations is:
Allowed values
- Controlled by LN
- Phantom
-
The use of phantom subassemblies as part of the job shop bill of material are:
Allowed values
- Controlled by LN
- Controlled by PLM
- Replaces Item
-
The replacement of items that are part of the job shop bill of material is:
Allowed values
- Controlled by LN
- Controlled by PLM
- Alternatives Present
-
The management of alternative materials is:
Allowed values
- Controlled by LN
- Allow Multiple Alternatives
-
The division of the estimated material quantities over available material options is:
Allowed values
- Controlled by LN
- Print on Order Document
-
The printing of bill of material component on the order document is:
Allowed values
- Controlled by LN
- Standard Configuration
-
The job shop bill of material line being part of the standard configuration is:
Allowed values
- Controlled by LN
- Exceptions Present
-
The presence of exceptions is:
Allowed values
- Controlled by LN
- Reference Designator Present
-
The presence of reference designators is:
Allowed values
- Controlled by LN
- Specify Material Offset
-
The lead-time offset is:
Allowed values
- Controlled by LN
- Controlled by PLM
- Material Offset
-
The material offset is:
Allowed values
- Controlled by LN
- Controlled by PLM
- Material Offset Unit
-
The time unit in which the material offset is calculated is:
Allowed values
- Controlled by LN
- Controlled by PLM
- Report Material
-
Material reporting is:
Allowed values
- Controlled by LN
- Supplied by Subcontractor
-
Which materials are supplied by subcontractor is:
Allowed values
- Controlled by LN
- Inherit Demand Peg
-
Demand pegs are:
Allowed values
- Controlled by LN
- Customer Furnished Material
-
The use of customer furnished materials is:
Allowed values
- Controlled by LN
- Contains Customer Furnished Material
-
The addition of customer furnished materials to the job shop bill of material is:
Allowed values
- Controlled by LN
- Percentage Required
-
The percentage of raw material that must be available before the operation can be started is:
Allowed values
- Controlled by LN
- Controlled by PLM
- Inherit Warehouse if Product is used as Phantom
-
The inheritance of the warehouse if the parent item is a phantom is:
Allowed values
- Controlled by LN
- Material Text
-
The material text is:
Allowed values
- Controlled by LN
- Controlled by PLM
- Alternative Material
-
- Alternative Position by PLM
- If this check box is selected, the application uses the
alternative position by PLM.Note: This check box is enabled if the Alternative Materials is implemented.
- Alternative Priority by PLM
- If this check box is selected, the application uses the PLM as
an alternative priority. Note: This check box is enabled if the Alternative Materials is implemented.
- Alternative Item by PLM
- If this check box is selected, the application uses a PLM Item
as the alternative item. Note: This check box is enabled if the Alternative Materials is implemented.
- Reference Designator
-
- Reference Designator by PLM
- If this check box is selected, the application uses PLM for
reference designator. Note: This check box is enabled if the Reference Designators is implemented.
- Quantity Reference Designator by PLM
- If this check box is selected, the application uses PLM for
quantity reference designator. Note: This check box is enabled if the Reference Designators is implemented.