Where-Used Job Shop List of Materials (tibom3110m100)

Use this session to view where specific materials are used in the job shop bill of materials.

Note: To use this session the Job Shop by Site parameter in the Concept Activation (tcemm4600m000) session must be set to Active.

Field Information

Item

The material ID.

Site

The site ID.

Product

The product ID.

Bill of Material

The ID of the bill of material (BOM) for which the list of material is displayed.

Revision

The bill of material revision.

BOM Quantity

The BOM quantity.

Position

The number of the JSBOM line.

Warehouse

The warehouse ID.

Lot Selection
This field is applicable for lot-controlled items. The values Any, Same, or Specific regard the special conditions for the delivery of lot items on order lines. The values also determine the way lot numbers are assigned.

Allowed values

Any

The goods received or shipped are not subject to specific lot conditions. You can use more than one lot.

Same

You can select any lot for receipt or shipment, but the entire receipt or shipment must have the same lot.

Specific

You can receive or ship only one, specific lot.

Net Quantity

The net quantity of material needed.

Scrap Quantity

The scrap quantity expected during production, independent of the order quantity. This is used to define the amount of material lost every time production is started, for example to test equipment.

Note: This value is defaulted from the Scrap Quantity in BOM Unit field, if the Use BOM Units check box is selected.
Scrap Percentage

The expected relative material loss, for example due to faulty components. The gross quantity should be increased to compensate for these material losses.

Length

This field can be used, together with the Width field and number of units, to calculate the net quantity.

The net quantity is the Length field multiplied by the number of units and multiplied by the Width field, if applicable.

In the Print Production Order Documents (tisfc0408m000) session, you can only print a sawing list if you have entered the Length field for the given component. If you have entered both the Length field and the Width field, you can print a cutting list.

Width

This field can be used, together with the Length field and number of units, to calculate the net quantity.

The net quantity is the Length field multiplied by the number of units and multiplied by the Width field, if applicable.

If you have entered both the Length field and the Width field, you can print a cutting list in the Print Production Order Documents (tisfc0408m000) session.

Size Unit

The unit of measurement used.

Number of Units

The number of times that the required quantity of the material, specified in the Length field and/or the Width field, appears in the product.

Operation

The ID of the operation where the material is used.

M-R Relations Present

If this check box is selected, material-routing relationships are present for the JSBOM component.

Phantom

If this check box is selected, the material or component is a phantom.

Text

If this check box is selected, text about the material is present.

Use-Up Item

The material from the previous BOM revision, which is now a use-up material. As long as the use-up material is present in inventory, it will be used instead of the material specified in the Item field.

Alternatives Present

If this check box is selected, alternative materials are linked to the JSBOM line.

Allow Multiple Alternatives

If this check box is selected, LN can distribute the net quantity of the material over multiple items. For example, the net quantity can be divided over the use-up material and the standard material or over the standard material and one or more alternative materials. If this check box is cleared, LN issues only a single item for this BOM line for one production order.

For examples, refer to Searching for alternative materials.

Print on Order Document

If this check box is selected, the JSBOM component is printed on the order document.

Standard Configuration

If this check box is selected, the JSBOM line is part of the product's standard configuration.

Note: When using unit effectivity, unit 0 represents the standard configuration.
Exceptions Present

If this check box is selected, the JSBOM line has exceptions linked to it. Exceptions are part of the unit effectivity concept.

Reference Designator Present

If this check box is selected, reference designators are present for the item.

Specify Material Offset

If this check box is selected, you can specify the lead-time offset.

Material Offset

The lead-time offset. LN uses the lead-time offset in capable-to-promise calculations. The date that a component must be available is calculated by subtracting the lead-time offset from the requirement date of the end item.

Note: You can only type the lead-time offset if the Specify Material Offset check box is selected.
Material Offset Unit

Select Hours or Days as the time unit in which you want to express the lead-time offset.

Supplied by Subcontractor

If you subcontract one or more operations, or an item's entire production process, you can choose whether or not to send material to the subcontractor to use for the subcontracted item.

If this check box is selected, the material is not sent to the subcontractor, but it is supplied by the subcontractor. Therefore, the material's planning and costing is not taken into account.

If this check box is cleared, and the material is linked to a subcontracted operation, the material is sent to the subcontractor.

Inherit Demand Peg

If a production order is transferred from Enterprise Planning to Job Shop Control , the order can have a demand peg.

Note: A specification is generated for the peg.

You can use this field to determine whether the material must have this demand peg as well.

Customer Furnished Material

If this check box is selected, the material is a customer furnished material.

Note: Only visible when the Customer Furnished Materials parameter are selected in the Implemented Software Components (tccom0100s000) session.

Contains Customer Furnished Material

If this check box is selected, the end-item is an item that is built using one or more customer furnished material.

Percentage Required

The percentage of raw material that must be available before the operation can be started.

Inherit Warehouse if Product is used as Phantom

Determines on which warehouse LN allocates the requirements for this component and from which warehouse it is issued if the component is a phantom.