Job Shop List of Materials (tibom3110m000)
Use this session to specify the materials and the related quantities that are required to manufacture a specific product.
- To use this session the Job Shop by Site parameter in the Concept Activation (tcemm4600m000) session must be set to Active or In Preparation.
- This session only applies if Job Shop by Site check box in the Implemented Software Components (tccom0500m000) is selected.
- You can modify the fields on the header section for a job shop bill of material
with a status of New only if one of these conditions is
met:
- The Product Lifecycle Management (PLM) is not the origin of the job shop bill of material.
- You can manually modify the PLM Controlled fields based on the settings defined in the Job Shop Bill of Material Control (tibom5100m000) session.
- The field is not controlled by PLM based on the template defined in the Job Shop Bill of Material Control (tibom5100m000) session.
- You can add a new revision to a job shop bill of material only if one of these
conditions is met:
- The Product Lifecycle Management (PLM) is not the origin of the job shop bill of material.
- You can manually add a revision based on the settings defined in the Job Shop Bill of Material Control (tibom5100m000) session.
Field Information
- Site
-
The site ID.
- Product
-
The product ID.
- Bill of Material
-
The ID of the bill of material (BOM) for which the list of material is displayed.
- BOM Quantity
-
BOM quantity
- Revision
-
The bill of material revision.
- Position
-
The number of the JSBOM line.
- Item
-
The material ID.
- Warehouse
-
The warehouse ID.
- Lot Selection
-
This field is applicable for lot-controlled items. The values Any, Same, or Specific regard the special conditions for the delivery of lot items on order lines. The values also determine the way lot numbers are assigned.
- Net Quantity in BOM Unit
-
The net quantity expressed in BOM unit. To use a BOM unit other than the item unit, an approved conversion factor must be defined. If the item unit is different from the BOM unit, the net quantity in item unit is calculated based on the approved conversion factor.
Note: This field is enabled only if:- The BOM Units of Material Lines check box is selected in the Product Engineering Parameters (timfc0100m000) session.
- The Use BOM Units check box is selected in the Job Shop Bills of Material (tibom3100m000) session.
- The Status of the Job Shop Bill of Material is set to New.
- Net Quantity
-
Note: This value is defaulted from the Net Quantity in BOM Unit field, if the Use BOM Units check box is selected.
- BOM Unit
-
The unit in which the related Net and Scrap quantities are expressed.
Note: This field is enabled only if:- This field is enabled only if:
- The BOM Units of Material Lines check box is selected in the Product Engineering Parameters (timfc0100m000) session.
- The Status of the Production Bill of Material is set to New.
- This field is enabled and mandatory if the Use BOM Units check box is selected in the Production Bills of Material (timfc3100m000) session.
- If the Use Bom Units check box is selected, the value specified for the BOM Unit is defaulted to the value of the item unit.
- This field is enabled only if:
- Scrap Percentage
-
The expected relative material loss, for example due to faulty components. The gross quantity should be increased to compensate for these material losses.
- Scrap Quantity
-
The scrap quantity expected during production, independent of the order quantity. This is used to define the amount of material lost every time production is started, for example to test equipment.
Note: This value is defaulted from the Scrap Quantity in BOM Unit field, if the Use BOM Units check box is selected. - Scrap Quantity
-
The scrap quantity to be specified in BOM unit.
Note: This field is enabled only if:- The BOM Units of Material Lines check box is selected in the Product Engineering Parameters (timfc0100m000) session.
- The Use BOM Units check box is selected in the Job Shop Bills of Material (tibom3100m000) session.
- The Status of the Job Shop Bill of Material is set to New.
- Length
-
You can use this field to calculate the net quantity if the inventory unit is Length or area unit. In case of area unit, this field is used in combination with Width.
The Length, Width, Size Unit and Number of Units fields apply only if the material has length or an area inventory unit, like meter and square meter. The inventory unit is defined in the Items (tcibd0501m000) session.
- Width
-
You can use this field to calculate the net quantity if the inventory unit is Width or area unit. In case of area unit, this field is used in combination with Length.
The Length, Width, Size Unit and Number of Units fields apply only if the material has length or an area inventory unit, like meter and square meter. The inventory unit is defined in the Items (tcibd0501m000) session.
- Size Unit
-
The unit of measurement for the Length and Width fields.
- Number of Units
-
The number of times that the required quantity of the material, specified in the Length field and/or the Width field, appears in the product.
- Operation
-
The ID of the operation where the material is used.
- M-R Relations Present
-
If this check box is selected, material-routing relationships are present for the JSBOM component.
- Phantom
-
If this check box is selected, the material or component is a phantom.
- Replaces Item
-
The material from the previous BOM revision, which is now a use-up material. As long as the use-up material is present in inventory, it will be used instead of the material specified in the Item field.
- Alternatives Present
-
If this check box is selected, alternative materials are linked to the JSBOM line.
- Allow Multiple Alternatives
-
If this check box is selected, LN can distribute the net quantity of the material over multiple items. For example, the net quantity can be divided over the use-up material and the standard material or over the standard material and one or more alternative materials. If this check box is cleared, LN issues only a single item for this BOM line for one production order.
For examples, refer to Searching for alternative materials.
- Visible on Order
- If this check box is selected, the material is visible on order. By default, this check box is selected. It can only be enabled floor stock items.
- Print on Order Document
-
If this check box is selected, the JSBOM component is printed on the order document.
- Standard Configuration
-
If this check box is selected, the JSBOM line is part of the product's standard configuration.
Note: When using unit effectivity, unit 0 represents the standard configuration. - Exceptions Present
-
If this check box is selected, the JSBOM line has exceptions linked to it. Exceptions are part of the unit effectivity concept.
- Reference Designator Present
-
If this check box is selected, reference designators are present for the item.
- Report Material
-
Specify the way material use is reported:
Allowed values
-
Backflush
This is an automatic calculation based on reported quantities. -
Manual
Reporting is done by an employee using the Machine Work List (tisfc4600m000) session. -
Undefined
This applies to converted bills of materials. Reporting is based on the Backflush parameter values in the Item - Production (tiipd0101m000) session.
-
- Specify Material Offset
-
If this check box is selected, you can specify the lead-time offset.
- Material Offset
-
The lead-time offset. LN uses the lead-time offset in capable-to-promise calculations. The date that a component must be available is calculated by subtracting the lead-time offset from the requirement date of the end item.
Note: You can only type the lead-time offset if the Specify Material Offset check box is selected. - Material Offset Unit
-
Select Hours or Days as the time unit in which you want to express the lead-time offset.
- Supplied by Subcontractor
-
If you subcontract one or more operation you choose whether to send material to the subcontractor to use for the subcontracted item.
- Inherit Demand Peg
-
If a production order is transferred from Enterprise Planning to Job Shop Control , the order can have a demand peg.
Note: A specification is generated for the peg.You can use this field to determine whether the material must have this demand peg as well.
- Customer Furnished Material
-
If this check box is selected, the material is a customer furnished material.
Note: Only visible when the Customer Furnished Materials parameter are selected in the Implemented Software Components (tccom0100s000) session. - Contains Customer Furnished Material
-
If this check box is selected, the end-item is an item that is built using one or more customer furnished material.
- Percentage Required
-
The percentage of raw material that must be available before the operation can be started.
- Inherit Warehouse if Product is used as Phantom
-
Determines on which warehouse LN allocates the requirements for this component and from which warehouse it is issued if the component is a phantom.
- Floor Stock
- Indicates the item is floor stock item.
- Text
-
If this check box is selected, text about the material is present.