Check Unit Effective Supply Consistency (tibom1218m000)
Use this session to check or simulate a check of the unit effectivity supply.
Field Information
- From Item
-
The item from which you want to check unit effectivity.
- Check Effectivity against Date
-
If this check box is selected, the session uses the bill of material (BOM) that is valid on the date that you specify.
If this check box is cleared, the session uses the current date.
- Check Date
-
Enter the check date used by LN to check the progress of activities. The check date must therefore be the same as the date on which you entered the progress of activities.
- Simulation Only
- If this check box is selected, the order lead time is not updated.