Planned Order (Assembly) (tiapl5636m000)

Use this session to view and maintain planned assembly orders for forecast quantities. The orders that are not yet fulfilled by actual orders or the unconsumed forecast demands, are considered.

Your Concept

Field Information

Scenario

The scenario ID.

Order Type

The type of order.

Allowed values

Not Applicable
Planned Assembly Order
Forecast Item

The code of the forecast item.

Base Model

The code of the base model.

Quantity

The order quantity.

Order Status

The status of the order.

Allowed values

Planned

You can still modify the planned order.

Firm Planned

LN does not change the start date or the order quantity of the order if you set the Planning Method field to Forward. LN does not change the finish date or quantity of the order if you set the Planning Method field to Backward.

You can still modify the planned order details.

Confirmed

The planned order has been confirmed. If the planned order belongs to the actual scenario, you can now transfer it to the execution level.

Planning Method

The calculation method for the planned start date and the planned finish date.

Allowed values

Forward

For a production order, the planning of the production order is based on a fixed start date. A delivery date is calculated from the order run time.

For a project, the network planning for the project is executed on the basis of a fixed start date. When you start the planning in the Generate Network Planning (tppss2240m000) session, LN determines the project's delivery date with a Forward planning method.

Backward

For a production order, the planning of the production order is based on a fixed delivery date. A start date is calculated from the order run time.

For a project, the network planning for the project is executed on the basis of a fixed delivery date. When you start the planning in the Generate Network Planning (tppss2240m000), LN determines the project's start date with a Backward planning method.

Requirement Date

The requirement date of the planned order.

Planned Start Date

The date and time when the employee starts working on the order.

Planned Finish Date

The date and time when the employee finishes the task for the order.

Planner

The employee responsible for planning the order.

Name

The name of the employee.

BOM Revision