Example 1: Activity has not yet started
Activity A has not yet started. No hours have been spent, there is no project structure, and there is no detailed capacity planning.
- Activity duration (project days): 15
- Rough capacity requirement : 200
- Earliest start date : day 4 week 44 year 92
- Percentage completed : 0%
The current date lies before the earliest start date. The following figure depicts activity A being carried out:
W | Workdays |
_ | Non-workdays |
The capacity load table assigned to the activity is shown in the following figure:
The capacity for activity A is 200 hours. The capacity load per week is as follows:
Week | Number of days | Percentage of Activity Duration | Percentage of Capacity Requirement | Difference Compared to Prev. Wk. | Capacity Requirement (per Week) |
44-92 | 2 | 13% | 17.3% | 17.3% | 34.6 |
45-92 | 6 | 40% | 40.0% | 22.7% | 45.4 |
46-92 | 9 | 60% | 40.0% | 0.0% | 0.0 |
47-92 | 12 | 80% | 70.0% | 30.0% | 60.0 |
48-92 | 12 | 80% | 70.0% | 0.0% | 0.0 |
49-92 | 15 | 100% | 100.0% | 30.0% | 60.0 |