Standard Cost Calculation by Project
You can calculate a simulated standard cost for all Project types. During a simulation, LN calculates, and updates the standard costs of customized items in the Standard Cost Calculation module. In the Project Control module, inventory is not revalued and the project price and the customized item price are not updated.
You can perform:
- Simulated standard cost calculations
- Estimated standard cost calculations
- Actual standard cost calculations
The following steps are taken if an estimated calculation of the standard cost is calculated:
-
Standard to order items
If a standard item with the order policy standard-to-order (STO) item is linked to a project, the cost calculation program analyzes the complete standard to order structure.
This complete standard to order structure is analyzed as if it were a customized item product structure. This product structure is then automatically exploded to the generic items level. This means that standard items made to order do not have to be included in the product structure to perform a correct calculation of material and operation costs.
As a result, any advantages resulting from batch production, in relation to setup costs, are not visible in the estimated project calculation. This applies if the same standard item made to order is linked to the project structure several times.
-
Standard phantom items
Comments referring to standard items made to order, also apply to standard phantom items linked to a project. The standard phantom structure is automatically analyzed by the cost calculation program. During this process, material and operation costs are included in the cost calculation of the project for phantoms. Comments made regarding batch production and lowering setup costs do not apply to phantoms.