Integrate Actual Operation Rates (tfcat2230m000)
Use this session to integrate the actual rates that are calculated in the Actual Costs by Dimension (tfcat2511m000) session or the Actual Costs by Reference Unit (tfcat2510m000) session into the operation rate in the Standard Cost Calculation module in Manufacturing (the Operation Rates (ticpr1150m000) session).
If the Integrate by Ledger Account check box is selected, the actual rates by ledger account (as calculated in the Actual Costs by Reference Unit (tfcat2510m000) session) are integrated.
LN uses the following sessions in order
- Integration Scheme for Standard Cost Calculation (tffbs1530m000) session
- Defaults for Standard Cost Calculation (tffbs1531m000) session to determine from what ledger account, dimension type, dimension, reference unit, or combination the surcharges must be integrated into the operation rate code and/or PCS-Project.
Field Information
- Standard Cost Calculation Code
-
Enter the standard cost calculation that will be used to calculate the standard cost in Standard Cost Calculation module.
- Unit for Hours
-
Enter a time unit to integrate the hours.
- Standard Calculation
-
If this check box is selected, LN integrates actual rates for the standard cost calculation in the Standard Cost Calculation module.
- Project / Budget Calculation
-
If this check box is selected, LN integrates actual rates for the project cost calculation in the Project Control module.
- Integration by Cost Type
-
If this check box is selected, LN integrates the rates as calculated in the Actual Costs by Reference Unit (tfcat2510m000) session.
- Overwrite Operation Rates
-
If this check box is selected, LN overwrites existing operation rates in the Standard Cost Calculation module and the Project Control module.
- Print Process Report
-
If this check box is selected, LN prints a process report.