Consolidate Planned Delivery Lines (tdsls3220m000)

Use this session to consolidate sales schedule lines on planned warehouse orders after sales schedule approval.

For approved sales schedule lines, planned warehouse orders already exist.

To consolidate sales schedule lines during approval, use the Approve Sales Schedules (tdsls3211m000) session.

Note: Updates to planned warehouse orders are logged as messages in the Message Log (tcstl1500m000) session, which is shown as a tab in the Sales Schedule (tdsls3611m000) session.

Field Information

Simulate

If this check box is selected, consolidation is only simulated, not processed.

Consolidate Options for Planned Delivery Lines
Move Past Requirements

If this check box is selected, for schedule lines with a requirement start date in the past, the New Requirement Start Date is used when consolidating sales schedule lines on planned warehouse orders.

Note: You cannot select this check box if the New Requirement Start Date is in the range of Original Requirement Start Date From and Original Requirement Start Date To and the Combine Planned Delivery Lines check box is also selected.
New Requirement Start Date

The new requirement start date used to consolidate schedule lines with a requirement start date in the past.

Move Nonpattern Requirements

If this check box is selected, for schedule lines with a requirement start date not derived from the Delivery Pattern, the New Requirement Start Date is used when consolidating sales schedule lines on planned warehouse orders.

Note: You cannot select this check box if the New Requirement Start Date is in the range of Original Requirement Start Date From and Original Requirement Start Date To and the Combine Planned Delivery Lines check box is also selected.
New Requirement Start Date

The new requirement start date used to consolidate schedule lines with a requirement start date not derived from the Delivery Pattern.

Combine Planned Delivery Lines

If this check box is selected, for schedule lines with a requirement start date that is in the range of Original Requirement Start Date From and Original Requirement Start Date To, the New Requirement Start Date is used when consolidating sales schedule lines on planned warehouse orders.

Note: You cannot select his check box if the new requirement start date of one of the other options is in the range of Original Requirement Start Date From and Original Requirement Start Date To.
New Requirement Start Date

The new requirement start date used to consolidate schedule lines with a requirement start date that is in the range of Original Requirement Start Date From and Original Requirement Start Date To.

Original Requirement Start Date From

The first date in the range of original requirement start dates that must be changed for consolidation.

Original Requirement Start Date To

The last date in the range of original requirement start dates that must be changed for consolidation.