Process Delivered Purchase Schedules (tdpur3223m000)
Use this session to process purchase schedule lines.
A purchase schedule line is ready for processing if its status is:
- Final Receipt and Financials is not implemented.
- Invoiced and Financials is implemented.
- Final Receipt for consignment schedules.
- Final Receipt and all delivered goods are rejected. No invoice is expected.
- Final Receipt and intercompany settlement transactions can be generated for the buy-from business partner. For this purpose, you must select the Intercompany Settlement check box in the Business Partner (tccom4100s000) session.
Although a purchase schedule line is ready for processing, the schedule line cannot be processed if an inspection order is still open.
When a purchase schedule line is processed, LN:
- Inserts a turnover history record.
- Updates called quantities/amounts and invoiced quantities/amounts for purchase contracts.
- Sets the status of the purchase schedule line to Processed.
- Updates the average purchase price if Financials is not implemented.
- Updates the invoice-from business partner's balance.
- Changes the status of the schedule header from Termination in Process to Terminated when all lines are processed or canceled.
Note: You need not process pull forecast schedule lines because
these lines are used for planning purposes only. No receipts are made on pull
forecast schedule lines.
Field Information
- Process up to Date
-
The date until which you want LN to process the purchase schedule data.
- Print Errors
-
If this check box is selected, if errors occur during the processing process, LN prints an error report.