Purchase Schedule - Receipts (tdpur3115m200)
Use this session to:
- View all (partial) receipts that are made for a particular purchase schedule (line) in Warehousing.
- View, maintain, and confirm all (partial) receipts that are made for a particular purchase schedule line with an administrative cost or service item.
Receipts in Warehousing
If a receipt is made in Warehousing, in the current session, LN searches for an existing record for a combination of Schedule, Receipt Number, Packing Slip, and Receipt Date. If found, the following fields are updated:
- Packing Slip Quantity
- Received Quantity
- Rejected Quantity
- Approved Quantity
- Suppliers ASN, if ASNs are used in a company.
If the combination is not found, LN creates a new record in this session.
For push schedules, goods are received against a blanket warehouse order. During receipt, the oldest requirement on the purchase schedule is fulfilled first. As a result, one receipt can be made for several purchase schedule lines. For an example of receiving goods on a push schedule, refer to Purchase schedule cumulatives.
For pull call-off schedules, goods are received against a specific reference ID. This reference ID is displayed in the Reference ID field of the Purchase Schedule Lines (tdpur3111m000) session. As a result, for every pull schedule line, a warehousing order line exists with a position number and a reference number, and only one receipt can be made for one purchase schedule line.
After a receipt is confirmed in Warehousing, you can perform a receipt correction of uninspected goods in the Receipt Correction (whinh3121s000) session. If you change the received quantity of an already confirmed receipt on a pull call-off schedule line, LN updates:
- The Received Quantity field in the Purchase Schedule Lines (tdpur3111m000) session.
- The Received Quantity field in the Purchase Schedule - Receipts (tdpur3115m200) session.
If you change the received quantity of an already confirmed receipt on a push schedule, a distinction is made between increasing the received quantity and decreasing the received quantity. For more information, refer to Receipts on push schedule lines.
Receipts in Purchase Control
For cost or service items, you must specify and confirm the receipt of goods in the Purchase Schedule - Receipts (tdpur3115m200) session.
To specify and confirm a receipt:
- In the Purchase Schedule Lines (tdpur3111m000) session, select the applicable purchase schedule line.
- From the appropriate menu in the Purchase Schedule Lines (tdpur3111m000) session, select . The Purchase Schedule - Receipts (tdpur3115m200) session starts.
- In the Purchase Schedule - Receipts (tdpur3115m200) session, specify the purchase schedule line's receipt details and select from the appropriate menu of the current session to confirm the receipt.
Field Information
- Schedule
-
The number of the purchase schedule.
- Receipt Amount
-
The received quantity * the price.
Note: If a receipt is confirmed of a configured item that deviates from the ordered configured item, in the Sequence Shipping data (tdpur3517m000) session, LN retrieves the price and discounts from the last Sent sequence shipping schedule line revision with a configured item that is equal to the received configured item. Otherwise, the price and discounts from the Purchase Schedule Lines (tdpur3111m000) session are used to calculate the amount. - Currency
-
The purchase schedule's currency.
The purchase currency is retrieved from the Currency field in the Purchase Schedules (tdpur3110m000) session.
- Receipt Number
- Receipt Line
-
The number of the receipt line that is linked to the receipt number.
- Packing Slip
-
The packing slip number.
LN retrieves the packing slip number and the packing slip information from the Warehouse Orders module.
- Packing Slip Quantity
-
The shipped quantity as mentioned on the packing slip, expressed in the purchase unit.
- Packing Slip Quantity
-
The shipped quantity as mentioned on the packing slip, expressed in the inventory unit.
- Approved Quantity
-
The approved quantity, expressed in the purchase unit.
If inspection of received goods is mandatory in a company, LN retrieves the approved quantity from the Warehouse Inspections Overview (whinh3122m000) session. If received goods need not be inspected, this field is equal to the value of the Received Quantity field.
Note: In the Inspection field of the Purchase Contract Lines (tdpur3101m000) session and/or in the Inspection field of the Items - Purchase Business Partner (tdipu0110m000) session, you can define for a company whether goods must be inspected upon receipt.In case of a receipt correction on a push schedule, in the current field, a negative value can be displayed.
- Approved Quantity
-
The approved quantity, expressed in the inventory unit.
- Rejected Quantity
-
The rejected quantity, expressed in the purchase unit.
If inspection of received goods is mandatory in a company, LN retrieves the rejected quantity from the Warehouse Inspections Overview (whinh3122m000) session. If received goods need not be inspected, this field is always set to zero.
Note: In the Inspection field of the Purchase Contract Lines (tdpur3101m000) session and/or in the Inspection field of the Items - Purchase Business Partner (tdipu0110m000) session, you can define for a company whether goods must be inspected upon receipt. - Rejected Quantity
-
The rejected quantity, expressed in the inventory unit.
- Status
-
The purchase schedule line's status.
If goods are received in the Warehouse Receipt (whinh3512m000) session, only the purchase schedule lines with one of the following statuses are displayed in the Purchase Schedule - Receipts (tdpur3115m200) session:
- Partial Receipt
- Final Receipt
For push schedules, these statuses represent the following:
Partial Receipt
- Schedule Quantity > Received Quantity, or
- Total Approved Quantity + Rejected Quantity < Received Quantity.
Final Receipt
- Schedule Quantity = Received Quantity, and
- Total Approved Quantity + Rejected Quantity = Received Quantity.
For pull call-off schedules, the status of the purchase schedule line/ purchase schedule receipt detail depends on the value of the Final Receipt check box on the Lines tab of the Warehouse Receipt (whinh3512m000) session:
- If this check box is selected, the purchase schedule line/ purchase schedule receipt detail automatically receives the status Final Receipt.
- If this check box is cleared, the purchase schedule line/ purchase schedule receipt detail automatically receives the status Partial Receipt.
Allowed values
- Created
-
Assigned as soon as a line is created by IRP, Project , SIC, or if the line is inserted manually.
- Approved
-
Assigned to lines that are approved and that can be copied to an order.
- Disapproved
-
Assigned to lines that are rejected during the approval process. Lines that were previously communicated to the supplier, and for which quantities are reduced, receive the status Canceled.
- ASN Received
-
Assigned to lines on which an advance shipping notification is received. If CUMs are registered, the shipped CUM is now adjusted.
- Order Generated
-
- For push schedules, this status is assigned to lines on which an advance shipping notification is received that is deleted again in the Shipment Notices (whinh3100m000) session. As a result, the push schedule line can only receive the status Order Generated from the status ASN Received.
- For pull call-off schedules, this status is assigned to lines for which a warehousing order is generated.
- Partial Receipt
-
Assigned to lines on which some goods have arrived, but on which not everything is received or approved yet.
- Final Receipt
-
Assigned to lines on which all required goods have arrived and are approved.
- Invoiced
-
Assigned to lines for which the invoice is approved. As a result, the invoice date is now filled.
- Processed
-
Assigned to lines whose requirements are processed in the Process Purchase Schedules (tdpur3223m000) session.
- Canceled
-
Assigned to lines that are canceled because the goods are no longer required.
- Confirmed
-
If this check box is selected, the receipt is confirmed for a combination of receipt number, packing slip number, and receipt date.
Note:- If receipts are made in Warehousing , this check box is automatically selected. The reason for this is that Warehousing only sends confirmed receipts to Purchase Control .
- You can only delete a confirmed receipt if the purchase schedule line has the status Processed.
If the purchase schedule line includes an administrative cost or service item, receipts on the schedule line must be maintained and confirmed in the Purchase Schedule - Receipts (tdpur3115m200) session. If you select from the appropriate menu of the Purchase Schedule - Receipts (tdpur3115m200) session, the schedule's cumulative quantities are updated, as well as the Purchase Schedule Lines (tdpur3111m000) session. After confirmation of the receipt, you can no longer change the receipt.
- Specification
-
If this check box is selected, a specification is linked to the purchase schedule receipt.
- Option List ID
-
option list ID
Note: Click to view the received configured item 's options and features in the Option List (tcibd4522m000) session. - Lot
-
- Serial Number
-
- Final Receipt
-
If this check box is selected, the entered receipt is the final receipt for the purchase schedule line.
Subsequently, if you select Final Receipt. You must only confirm the receipt of an administrative item (cost or service).
from the appropriate menu of the current session, the schedule line's status changes toIf this check box is cleared, the entered receipt is a partial receipt for the purchase schedule line.
Subsequently, if you select Partial Receipt.
from the appropriate menu of the current session, the schedule line's status changes toNote: You must only confirm the receipt of an administrative item (cost or service). - Shipping Date
-
The date on which the items are shipped.
Note:This date must be filled if the following applies:
- The Self-Billing check box is selected for the purchase schedule.
- The Payment is set to Pay on Receipt for the purchase schedule line.
- The Self-Billing Date Type is set to Shipping Date in the Invoicing Terms and Conditions (tctrm1145m000) or Buy-from Business Partner (tccom4120s000) sessions.
Default value
If the shipping date is mandatory, the default value is the receipt date. Otherwise, this field is empty.
- Receipt Date
- Suppliers ASN
-
shipment ID
- Manufacturer Part Number
-
The manufacturer part number (MPN) for the scheduled item.
Note: The MPN must belong to the MPN set that is linked to the purchase schedule line. - Manufacturer
-
The manufacturer that is linked to the manufacturer part number (MPN).
- Engineering Item Revision
-
The revision of the engineering item.
- Customer Item Revision
-
The revision of the customer's item code.
Note: You can specify revisions for customer item codes in the Business Partner Item - Revisions (tcibd0114m000) session. - ASN Line
-
The line number of the supplier's advance shipping notice.
- Carrier/LSP
-
The code of the carrier.
- Peg Distribution
-
If this check box is selected, a peg distribution is linked to this Purchase Schedule Receipt.
- Schedule Type
-
The type of the purchase schedule.
Receipts can only be made for push schedules and pull call-off schedules.
- Schedule Line
- Item
- Sequence
-
The number that identifies a (partial) receipt of a purchase schedule line.
- Receipt Log Date
-
The date on which the receipt is registered in LN, which is the date and time a user confirms the receipt. This date can differ from the receipt date, because the receipt date reflects the physical receipt of the goods.
Note: This date is used by Manufacturing to calculate standard costs in the past and relates to the valuation method lower cost or market value (LCMV). - Received Quantity
-
The received quantity, expressed in the purchase unit.
Note:- The received quantity cannot be greater than the ordered quantity on the purchase schedule line.
- In case of a receipt correction on a push schedule, in the current field, a negative value can be displayed.
- Purchase Unit
- Received Quantity
-
The received quantity, expressed in the inventory unit.
- Inventory Unit
- First Shipment
- The first shipment linked to the purchase invoice.
- Goods in Transit
- The number of goods that are in transit is linked to purchase order line.
- Goods in Transit in Inventory Unit
- The number of goods that are in transit is linked to purchase order line in the inventory unit.
- Accepted Rejected Goods
-
If this check box is selected, the goods for this receipt were received from the reject location.
- Reason for Rejection