Copy Purchase Requisitions (tdpur2204s000)

Use this session to copy an existing requisition to a new requisition or an existing requisition. You can copy active requisitions and requisitions from the history files.

In this session you can copy all lines from the source requisition. The destination order series, selected from the first free numbers, determines the new requisition number.

Click Select Lines... to access the Purchase Requisition Lines (tdpur2502m000) session. From here, you can select individual lines and copy them to the new or existing requisition.

Note: When you copy a requisition to an existing requisition, the status of the destination requisition must be Created or Modified.

Field Information

Source
Copy from History

If this check box is selected, you can copy a requisition from history.

Requisition

The number of the source purchase requisition.

Requester

The employee code of the source requisition's requester.

Purchase Office

The source requisition's purchase office.

Target
Requisition

The number of the target purchase requisition.

Requester

The employee code of the target requisition's requester.

Purchase Office

The target requisition's purchase office.

Requested Date

The requested delivery date for the copied items.

Copy All Lines

If this check box is selected, LN copies all lines from the original requisition.

If this check box is cleared, you can access the Select Lines... button. Then you can select which lines are copied.

Copy Peg Distribution

If this check box is selected, and an original requisition line has a linked peg distribution, this distribution is also copied to the target requisition line.

Peg Change Reason

The change reason for manually creating the pegged supply. The reason must be specified only if the Manual Project Peg Modification check box is selected in the Project Pegging Parameters (tcpeg0100m000) session.

The project peg changes and the reason codes are logged in the Cost Peg Audit History (tpctm2500m000) session.

Note: The reason code must be of the type Project Peg Audit History and applies to all pegs in the peg distribution.

Copy Additional Information

If this check box is selected, additional information from the original requisition (line) is copied to the target requisition (line).

Copy Texts

If this check box is selected, LN copies any text associated with the original requisition.

Note: If you copy a requisition to a new requisition, both header and line texts are copied. If you copy a requisition to an existing requisition, only the line texts are copied.