Linked RFQ Data (tdpur1502s000)
Use this session to view the linked objects for a request for quotation (RFQ) line.
Linked objects are objects from which the RFQ line is generated and objects to which the response line is converted.
Field Information
- RFQ
-
The number of the request for quotation (RFQ).
- Line
-
The number of the request for quotation (RFQ) line.
- Sequence
-
The request for quotation (RFQ) line's sequence number, which is greater than one if it includes an item that can be an alternative for the preferred item.
You must manually specify alternatives in the RFQ Lines (tdpur1502m000) session.
Example
The sequence numbers defined in the current field, represent the RFQ lines in the most suitable alternative sequence. So, sequence number one represents the first preferable item that can be an alternative for the originally preferred item, sequence number two represents the second item that can be an alternative, and so on.
- Bidder
-
Note: If this field is specified, this session refers to a response line. If this field is empty, this session refers to an RFQ line.
- Origin
-
- Original Document
-
The original object from which the RFQ line is generated.
- Original Document Line
-
The original object line from which the RFQ line is generated.
- Converted to Document
-
- Purchase Order
-
The number of the purchase order to which the response line is converted.
- Purchase Order Line
-
The position number of the order line to which the response line is converted.
- Purchase Order Sequence
-
The sequence number of the order line to which the response line is converted.
- Purchase Contract
-
The number of the purchase contract to which the response line is converted.
- Contract Line
-
The number of the purchase contract line to which the response line is converted.
- Price Book
-
The number of the supplier price book to which the response line is converted.
- Discount Schedule
-
The discount schedule that is linked to the supplier price book to which the response line is converted.
- Linked Document
-
- Production Order
-
The production order for which the RFQ line is generated.
- Operation
-
The operation for which the RFQ line is generated.
- Estimated Material Line Number
-
The number of the linked estimated material line with the supplied material to the subcontractor.
- Subcontrator Site
-
The Site of the subcontractor.
Note: This field is displayed only if Resource by Site is active. - Routing
-
The routing for which the RFQ line is generated.
- Operation Sequence
-
The operation sequence for which the RFQ line is generated.
- Manufactured Item
-
The main item for which the RFQ line is generated.
- Task
-
The task for which the RFQ line is generated.
Note: This field label must be displayed as ‘Reference Operation’ when Job Shop by Site concept is active. - Manufactured Item
-
The manufactured item of the routing for which the RFQ line is generated.
- Service Order
-
The service order for which the RFQ line is generated.
- Service Order Line
-
The service order line for which the RFQ line is generated.
- Maintenance Work Order
-
The work order for which the RFQ line is generated.
- Maintenance Work Order Line
-
The work order line for which the RFQ line is generated.
- Reference Activity
-
The reference activity for which the RFQ line is generated.
- Material Supply Information
-
If this check box is selected, the RFQ line includes a subcontracted item with linked material supply information.