Recalculate Landed Costs (tclct2800s000)
Use this session to recalculate landed cost lines.
Note:
You can use this session to:
- Recalculate landed costs if the Recalculate Landed Costs field is No in the Landed Costs Parameters (tclct0100m000) session.
- Recalculate the Manual and Modified landed costs if the Recalculate Landed Costs field is Automatic in the Landed Costs Parameters (tclct0100m000) session.
- Rebuild the landed costs for advance shipment notice (ASN) (lines). This can be required when the ASN (line) is created through EDI, but the landed cost lines could not be created. After resolving the cause of the error(s), the landed costs can be recalculated with this session.
- Log how a landed cost (freight) amount is calculated or why no amount can be calculated.
Field Information
- Recalculate
-
- Header Landed Costs
-
If this check box is selected, LN recalculates landed cost lines at the header level.
- Line Landed Costs
-
If this check box is selected, LN recalculates landed cost lines at the line level .
- Options
-
- Overwrite Manual and Modified Landed Costs
-
If this check box is selected, LN also recalculates ( Modified) landed cost lines (origin: Manual).
- Log Freight Amount Calculation
-
If this check box is selected, for landed cost lines whose Calculation Method field is By Freight Management, you can log how the freight amount is calculated or why no amount can be calculated.
Note: You cannot select this check box if a freight order already exists for the originating order line. In this case, the landed cost are overwritten with the estimated or actual landed (freight) costs during the Freight procedure.