Process Received Item Engineering Revision (tcibd0260m100)
Use this session to process the item engineering revisions data that is received from Product Lifecycle Management (PLM). You can only process the revisions with the Status set to Received.
When the item engineering revisions data is processed, the related item data is created or updated in the in the Items (tcibd0501m000) session and a revision is added in theItem Engineering Revisions (tcibd0150m000) session.
Note: This session can be accessed only if:
- The Engineering Revisions check box is selected in the Implemented Software Components (tccom0100s000) session.
- The Originating App field is set to these
values in the Item Base Data Parameters (tcibd9199m000) session:
- IBD
- PLM (Internal)
- PLM (external)
You can also access this session using the Process option from the menu in the Received Item Engineering Revisions (tcibd0160m000)session.
Field Information
- Selection
- Use the fields in the Selection group box to specify the range of received item engineering revisions data that must be processed.
- Options
-
- Approve
- If this check box is selected, the created item revision with the Status updated to Approved.
- Process Report
- If this check box is selected, LN prints a process report with the received item engineering revisions that are successfully processed.
- Error Report
- If this check box is selected, LN prints an error report with the received item engineering revisions that are not processed successfully.