Test Calendar Date Planning (tcccp0121m000)

use this session to plan the activities for a project based on the calendar date.

Field Information

Company

The code of the company for which the planning is done.

Calendar

The calendar code based on which the planning is done.

/

The availability type associated with the calendar.

Time Zone

The time zone for which the planning is done.

Date

The date and time for which the planning is done.

Lead Time

The lead time based on which the planning is done.

Lead Time Unit

The lead-time unit for the lead time.

Plan Method

The method used for the planning of the activities.

Allowed values

Forward

For a production order, the planning of the production order is based on a fixed start date. A delivery date is calculated from the order run time.

For a project, the network planning for the project is executed on the basis of a fixed start date. When you start the planning in the Generate Network Planning (tppss2240m000) session, LN determines the project's delivery date with a Forward planning method.

Backward

For a production order, the planning of the production order is based on a fixed delivery date. A start date is calculated from the order run time.

For a project, the network planning for the project is executed on the basis of a fixed delivery date. When you start the planning in the Generate Network Planning (tppss2240m000), LN determines the project's start date with a Backward planning method.

If this check box is selected, the early start and finish date is used for planning.

Specify when the calendar data must be considered for planning.

Allowed values

Start

The earliest start date is considered for planning.

Finish

The earliest finish date is considered for planning.

Calendar Start Date

The planned start date and time calculated by LN.

Calendar End Date

The planned start date and time calculated by LN.