Non-working Days (tcccp0119m000)
Use this session to view and manage days that are not available for production and cannot be scheduled in a specific calendar.
Field Information
- Calendar Code
-
The days you want to view, or specify unavailable.
- Period
-
Displays for which day, week, 4 weeks, month, quarter, half year, or year LN displays the unavailable days.
To change the period definition, click one of the following icons:
To change the period definition to the values mentioned above or to one of the following options, on the appropriate menu, click
:Default value
- Period Dates
-
Displays the start and the end date of the period in which the unavailable days are specified.
- Date
-
Displays the date of an unavailable day. To define a new unavailable day for the specified calendar, click Add a New Record.
- Description
-
Specify why a specific day is not available for the calendar code.