Resource Assignments (qmptc1160m000)
Use this session to assign and maintain resources for the Quality related business objects such as non-conformance report (NCR), corrective action plans (CAP) tasks or inspection orders lines.
- You can assign more than one resource only if the Resource Management Implemented check box is selected in the Quality Management Parameters (qmptc0100m000) session.
- You can access this session from the Non-Conformance Reports (qmncm1100m000) session, the Inspection Order Lines (qmptc1101m000) session, and the Tasks tab of the Corrective Action Plan (qmcpl1100m900) session or the Tasks (qmcpl1105m000) session.
Field Information
- Document Type
-
The category or type of the document.
Allowed values
- Inspection Order
- Certificate of Conformance
- Failure Reporting Analysis
- Non-Conformance Report
- Ship to Stock
- Ship to Stock Rule
- Corrective Action Plan
- First Article Inspection
- Root Cause Analysis
Note:By default, the value is set to:
- Inspection Order, if this session is accessed from the Inspection Order Lines (qmptc1101m000) session.
- Non-Conformance Report, if this session is accessed from the Non-Conformance Reports (qmncm1100m000) session.
- Corrective Action Plan, if this session is accessed from the References menu on the Tasks tab of the Corrective Action Plan (qmcpl1100m900) session or from the Tasks (qmcpl1105m000) session.
- Business Object
-
The code of the business object.
Note:By default, LN sets the value to:
- Inspection Order number, if this session is accessed from the Inspection Order Lines (qmptc1101m000) session.
- Non-Conformance Report number, if this session is accessed from the Non-Conformance Reports (qmncm1100m000) session.
- Corrective Action Plan number, if this session is accessed from the References menu on the Tasks tab of the Corrective Action Plan (qmcpl1100m900) session or from the Tasks (qmcpl1105m000) session.
- Status
-
The status of the resource assignment.
Allowed values
- Not Started
- In Progress
- Completed
- Canceled
Note: By default, this value is set to Assigned. - Non-Conformance Type
-
The type of non-conformance.
Allowed values
- Material
- Non-Material
Note:- By default, LN sets the value to:
- Material
- If this session is accessed from the Non-Conformance Reports (qmncm1100m000) session and only the non-conforming material data is specified in the Material tab of the session.
- If this session is accessed from the Inspection Order Lines (qmptc1101m000) session.
- If this session is accessed from the References menu on the Tasks tab of the Corrective Action Plan (qmcpl1100m900) session or from the Tasks (qmcpl1105m000) session.
- Non-Material, if this session is accessed from the Non-Conformance Reports (qmncm1100m000) session and the non-material related data is specified in the Non-Material tab of the session.
- Material
- If both the non-conforming material and the non-material related data are specified in the Non-Conformance Reports (qmncm1100m000) session, LN defaults this value to Non-material. However, you can modify the value.
- Line
-
The line number of the related Document Type.
Note:- If this session is accessed from the Non-Conformance Reports (qmncm1100m000) session and:
- The Non-Conformance Type is Material, the value in this field is set to 1.
- The Non-Conformance Type is Non-Material, the value in this field is set to 2.
- If this session is accessed from the Inspection Order Lines (qmptc1101m000), LN defaults the Line number.
- If this session is accessed from the References menu on the Tasks tab of the Corrective Action Plan (qmcpl1100m900) session or from the Tasks (qmcpl1105m000) session, LN defaults the Task number.
- If this session is accessed from the Non-Conformance Reports (qmncm1100m000) session and:
- Sequence
-
The sequence number.
- Employee
-
The code of the employee assigned as a resource to the business object (NCR, CAP task or inspection order line).
- Name
-
The description or name of the code.
- Time Estimate
-
The estimated time required to perform the activity.
- Time Unit
-
The unit in which the time is expressed.
- Description
-
The description or name of the code.
- Planned Start Date
-
The date on which the resource plans to initiate the business object (NCR, CAP task or inspection order line) related activity.
Note: LN defaults this value based on the date specified for the business object from which this session is accessed. - Planned Completion Date
-
The date on which the resource plans to complete the business object (NCR, CAP task or inspection order line) related activity.
Note: LN defaults this value based on the date specified for the business object from which this session is accessed. - Actual Start Date
-
The actual date on which the resource initiates the business object (NCR, CAP task or inspection order line) related activity.
- Actual Completion Date
-
The actual date on which the resource completes the business object (NCR, CAP task or inspection order line) related activity.
- Appointment
-
The code of the CRM appointment.
Note:- LN creates a CRM appointment for the business object (inspection order lines, NCRs, and CAP tasks) related activities only if the Inspection Order Assignments, Non-Conformance Report Assignments and Corrective Action Plan Assignments check boxes are selected in the Resource Management Parameters (tcrac0100m000) session.
- The inspection order lines, NCRs, and CAP tasks are visible as appointments in CRM.
- Resource Assignment Text
-
The additional information related to the resource assignment.