To Revert Outgoing Subassembly Actions
Outgoing Subassembly - Undo process
When you process an outgoing subassembly, the process of creating a warehouse order, a subcontracted activity, and an incoming subassembly is initiated. The status of the outgoing subassembly is set to processed.
It is possible that the specified action for the outgoing subassembly is not correct. For example, the subcontractor is unable to perform the task, and the work is required to be completed by another department, or the subassembly needs to be moved to a warehouse instead of a location. In such scenarios, you can use the Undo Confirm from the Action menu in the Work Order Outgoing Subassemblies (tswcs4150m000) session to revert the process.
Action Outgoing Subassembly To Location
When Action Outgoing Subassembly is set To Location, the subassembly is linked to the selected location. When you process this subassembly, an Incoming Subassembly is created for this location.
You can revert this process before the incoming subassembly is processed. The Confirmed check box is cleared, and the related incoming subassembly is deleted.
Action Outgoing Subassembly To Location for Work
When Action Outgoing Subassembly is set To Location for Work, the subassembly is linked to the selected location. A work order and an incoming subassembly is created. You can undo this process, as long as the Status of the related work order is Free. The Confirmed check box is cleared; the related work order and the incoming subassembly are deleted.
Action Outgoing Subassembly To Warehouse
When Action Outgoing Subassembly is set To Warehouse, the subassembly is linked to the selected warehouse. When you process this subassembly, a warehouse order is created to manage the inbound. You can undo this process, before the warehouse inbound procedure is initiated.
The Confirmed check box is cleared, the warehouse order, the planned inventory transaction and the incoming subassembly are deleted.
Action Outgoing Subassembly To Department
When Action Outgoing Subassembly is set To Department, the subassembly is maintained in a department other than the current department. Hence, the subassembly is returned to the warehouse of the service department, and transferred to the warehouse of the other department. A warehouse inbound and transfer order are created. Also a work order is created to manage the subassembly in the new department.
You can undo this process, if the warehouse inbound procedure is not initiated, and the Status of the related work order is still Free.
The Confirmed check box is cleared, the related warehouse order, the planned inventory transaction, the incoming subassembly, and the work order is deleted.
Action Outgoing Subassembly To Subcontractor
When Action Outgoing Subassembly is set To Subcontractor, the subassembly is managed by a subcontractor. When you process this subassembly, a new activity is linked to the work order.
You can undo this process, as long as the Status of the subcontracted activity is Free, and the warehouse inbound procedure is not initiated.
The Confirmed check box is cleared, and the related warehouse order, the planned inventory transaction and the related incoming subassembly are deleted. The subcontracted activity is also deleted. The Subcontracting Activity field in the Work Order Outgoing Subassemblies (tswcs4150m000) session is cleared.
Action Outgoing Subassembly To Scrap
When Action Outgoing Subassembly is set To Scrap, the subassembly is scrapped. When you process this activity, the Confirmed check box is selected, the serial status and the physical breakdown is updated.
The Confirmed check box is cleared, the serial status is updated after the new action is processed.