Inspecting scheduled items
If scheduled items must be inspected upon receipt, approved and rejected quantities are retrieved from Warehousing. The type of schedule, push schedule or pull call-off schedule, determines how the inspection results are communicated to Procurement.
Pull call-off schedules
If goods are inspected for a pull call-off schedule, LN completes these steps:
-
Purchase Schedule - Receipts (tdpur3115m200)
Searches for the unique combination of Schedule, Receipt Number, Packing Slip, Receipt Date, and Suppliers ASN number. - Updates the Rejected Quantity and Approved Quantity fields with the inspection results.
-
Purchase Schedule Lines (tdpur3111m000)
Searches for the unique combination of Schedule and Reference ID. - Updates the Rejected Quantity and Approved Quantity fields with the inspection results.
Push schedules
If goods are inspected for a push schedule, LN completes these steps: :
-
Purchase Schedule - Receipts (tdpur3115m200)
Searches for a combination of Schedule, Receipt Number, Packing Slip, Receipt Date, and Suppliers ASN number. Because one receipt can be made for several purchase schedule lines, several combinations can be found in the Purchase Schedule - Receipts (tdpur3115m200) session. - Updates the Rejected Quantity and Approved Quantity fields with the inspection results. If
several records are found in the Purchase Schedule - Receipts (tdpur3115m200) session, LN:
- Distributes the inspection results over the purchase schedule receipt detail records in the sequence of record with the oldest requirement date through the record with the youngest requirement date.
- First distributes the approved quantity and then the rejected quantity over the purchase schedule receipt detail records.
-
Purchase Schedule Lines (tdpur3111m000)
Searches for the purchase schedule line(s) that is/are linked to the updated record(s) in the Purchase Schedule - Receipts (tdpur3115m200) session. - Updates the Rejected Quantity and Approved Quantity fields with the inspection results.
Example
The following table shows the records in the Purchase Schedule - Receipts (tdpur3115m200) session after receipts are confirmed in Warehousing and before goods are inspected for a push schedule.
- Schedule number: 1000001
- Receipt number : 1
- ASN number : BP001
- Packing Slip : PS001
Schedule line | Requirement date | Receipt date | Required quantity | Received quantity | Approved quantity | Rejected quantity |
---|---|---|---|---|---|---|
10 | 13/2/2001 | 11/2/2001 | 10 | 10 | - | - |
20 | 14/2/2001 | 11/2/2001 | 5 | 5 | - | - |
30 | 15/2/2001 | 11/2/2001 | 20 | 5 | - | - |
Seven pieces are now inspected in Warehousing, of which three pieces are rejected and four pieces are approved. The following table shows the distribution of the inspection results in the Purchase Schedule - Receipts (tdpur3115m200) session.
Schedule line | Requirement date | Receipt date | Required quantity | Received quantity | Approved quantity | Rejected quantity |
---|---|---|---|---|---|---|
10 | 13/2/2001 | 11/2/2001 | 10 | 10 | 4 | 3 |
20 | 14/2/2001 | 11/2/2001 | 5 | 5 | 0 | 0 |
30 | 15/2/2001 | 11/2/2001 | 20 | 5 | 0 | 0 |
Finally, 13 pieces are inspected of which five pieces are rejected and eight pieces are approved. The following table shows the inspection results in the Purchase Schedule - Receipts (tdpur3115m200) session.
Schedule line | Requirement date | Receipt date | Required quantity | Received quantity | Approved quantity | Rejected quantity |
---|---|---|---|---|---|---|
10 | 13/2/2001 | 11/2/2001 | 10 | 10 | 7 | 3 |
20 | 14/2/2001 | 11/2/2001 | 5 | 5 | 5 | 0 |
30 | 15/2/2001 | 11/2/2001 | 20 | 5 | 0 | 5 |