Setup example for cost peg transfer rules
Cost peg transfer rules determine the sources and the destinations that are allowed for cost peg transfers. If no transfer rules are specified in the Cost Peg Transfer Rules (tcpeg1100m000) session, cost peg transfers from and to project cost pegs of all planning groups within the company are allowed.
Planning group | Project | Element | Activity | Inherit | Transfer In | Inherit | Transfer Out |
---|---|---|---|---|---|---|---|
A | Within Group | Across Groups |
Transfers to project pegs related to planning group A are allowed if the transfers originate from projects within the same planning group. Transfers out from these project pegs to project pegs related to projects across all planning groups of the company are allowed.
Planning group | Project | Element | Activity | Inherit | Transfer In | Inherit | Transfer Out |
---|---|---|---|---|---|---|---|
A | Within Group | Across Groups | |||||
A | A1 | X | Within Group | Within Project |
For project A1, which belongs to planning group A, the rules for transfers to the project are inherited from the planning group. Transfers out of project A1 are now restricted to cost pegs within the project. To all other projects belonging to planning group A, the general rules set for planning group A still apply.
Planning group | Project | Element | Activity | Inherit | Transfer In | Inherit | Transfer Out |
---|---|---|---|---|---|---|---|
A | Within Group | Across Groups | |||||
A | A1 | X | Within Group | Within Project | |||
A | A1 | E1 | ACT1 | Not Allowed | Not Allowed | ||
E2 | ACT2 | Not Allowed | X | Within Project | |||
B | Within Project | Within Project |
For cost account A/A1/E1/ACT1, no cost peg transfers in or out are allowed. Transfers to cost account A/A1/E2/ACT2 are not allowed, but transfers out are allowed to cost pegs within project A. The transfer-out rules are inherited from the transfer-out rules set for project A.