To update master-plan data
You can run the Initialize, Roll, and Update Scenario (cprpd4200m000) session (with the Generate Item/Channel Master Plan check box selected) to update item master plans and, if applicable, channel master plans for a range of plan items. This topic describes the various steps of the procedure involved.
In this procedure, no supply plan is generated. If you want to generate or update supply plans, run the Generate Master Planning (cprmp1202m000) session or the Generate Master Planning (Item) (cprmp1203m000) session.
If necessary, LN first rolls the scenario. See Using a rolling scenario. Next, LN (re)generates the master plans of the selected plan items. The plan items are processed in order of phase number.
The update procedure consists of the following steps:
A similar procedure is carried out when you choose Update in the Item Master Plan (cprmp2101m000) session.
When a scenario is rolled forward, LN updates the planning data for all plan items.
If you select the Multicompany Updating check box in the Initialize, Roll, and Update Scenario (cprpd4200m000) session, LN carries out the steps listed above for each logistic plan within the multicompany structure. See Multicompany planning.
After the update, LN updates all resource master plans that need to be updated.
You can view the results of the update in the following sessions:
- Item Master Plan (cprmp2101m000)
- Channel Master Plan (cpdsp5130m000)
- Resource Master Plan (cprmp3501m000)