cprrp domains
- Inventory
- Scheduled Receipts
-
The receipts made for a particular purchase schedule (line) in the Purchase Schedule - Receipts (tdpur3115m200) session.
- Item
-
The item order plan is generated based on all item transactions will be shown, whether the transaction contains a project peg or not. The user can only select an item, and not Project/ Element/ Activity.
- Item-Project
-
The item order plan is generated based on all item - PCA transactions for a selected item - project combination. User can only select item and Project. No Element or Activity can be selected.
- Item-Project Peg
-
The item order plan is generated based on all transactions for specific defined item - PCA combination. the user should be able to define item, Project, Element and Activity.
- Plan Item
-
If this value is selected the Print Subcontracint Forecast report is printed.
- Delivery Date
-
If this value is selected Print Subcontracting Forecast by Delivery Date report is printed.
- Plan Item
-
If this value is selected the Planned Inventory Movements by Item is printed. The Planned Inventory Movements by Item (Item Details) is printed only when the Print Details checkbox is selected.
- Order
-
If this value is selected the Planned Inventory Movements by Order report is printed.
- Supplying Item
-
The lead time can be a production or purchase lead time. The lead time depends on the actual source of the supplying plan item (which can be defined in another company – the supplying company).
Production N.A. Item - Production (tiipd0101m000) Purchase N.A. Items - Purchase (tdipu0101m000) Distribution filled Freight Management / Distance tables empty Supplying Relationships (cprpd7130m000) - Supply Lead Time
-
The distribution lead times. The distribution lead time is retrieved from the supplying relations or from distance calculations.
Supplying Relation Carrier Specified Lead time is retrieved in the following order: - Freight Management package
- Distance Tables
Carrier Not Specified The lead time as defined in the Supplying Relationships (cprpd7130m000)
- To be released
-
The planned order is ready for transfer to the execution level.
- Not to be released
-
The planned order cannot yet be transferred to the execution level.
- Planned
-
You can still modify the planned order.
- Firm Planned
-
LN does not change the start date or the order quantity of the order if you set the Planning Method field to Forward. LN does not change the finish date or quantity of the order if you set the Planning Method field to Backward.
You can still modify the planned order details.
- Confirmed
-
The planned order has been confirmed. If the planned order belongs to the actual scenario, you can now transfer it to the execution level.