Use this session to specify the statistics saved during order planning calculation per item.
Field Information
- Run Number
-
The identification number of the planning run.
- Session
-
The session from which Enterprise Planning retrieves the order planning.
- User
-
The name of the user responsible for planning.
- Start Date
-
The period for which statistical data is generated.
- Parallel bshell
-
The number of servers (bshells) used to calculate and actualize planning data.
Note:-
Distributing the calculations over multiple bshells improves performance.
-
Number is always zero (0) if parallell processing is not active.
-
- Sequence Number
- Plan Item
-
The ID of the plan item.
- Flagged
-
The run is flagged for inconsistencies.
- Phase Number
-
The phase number for order planning.
- Run time (msec)
-
If this check box is selected, you must specify the number of seconds that must be reached or exceeded for an item to be reported, if non of the other parameters were triggered.
- Abnormal End
-
If this check box is selected, the generation of an order plan failed for the specific item.
- Loop detected
-
If this check box is selected, loop in the bill of materials was detected during generation of the order plan.
- Times Planned
-
The number of times the selected item was planned.
- Inputs
-
The number of inputs used in the order planning generation.
Sales orders and purchase orders for the selected item, are examples of inputs possible.
Note: An item with a hundred sales orders, will have a longer planning run time than an item with one or two sales orders. - Planned Orders Created
-
The number of planned orders created on the last calculation.
- Planned Orders Updated
-
The number of planned orders updated on the last calculation.
- Planned Orders Deleted
-
The number of planned orders deleted on the last calculation.
- Non-Failure Messages
-
The number of non-critical exception messages generated.
- Failure Messages
-
The number of critical exception messages generated.
- Number of actions with Retry
-
The number of times generation of an order plan was retried.
- Phase Number Updates
-
The number of times the phase numbers for the selected item were updated.
- Initial Phase Number
-
The inital phase number for the selected item.