Project Resource Plan Chart (cprrp0732m000)
Use this session to display data from your resource order plan in a graphical format.
To display data:
- Specify a scenario and a plan level.
- Specify a work center.
- Specify a project.
- Specify the start date, the period length, and the maximum number of periods for the chart.
- Specify the type of data you want to view.
- Select a chart type.
- Click the button.
Most types of data shown in the chart correspond to fields in the resource order plan (see the Resource Order Plan (cprrp0530m000) session).
The following data is always displayed:
- Total Available Capacity
- Total Required Capacity
- Total Required Capacity for Project
Depending on the selected options, the chart can show more data.
Field Information
- Scenario
-
Specify the scenario for which LN must draw a chart of the planning data for the specified work center.
- Plan Level
-
The plan level of the plan items that use the work center for which LN must draw a chart.
- Work Center
-
The work center for which the chart is drawn.
- Project
-
The project for which LN must draw a chart.
- Start Date
-
The requested start date for the chart.
- Period Length
-
The period length for the division of the time scale of the chart.
- Number of Periods in View
-
The maximum number of periods shown on the chart.
- CTP Reservations
-
If this check box is selected, the chart displays the capacity used for capacity CTP reservations.
- Critical Capacity Requirements
-
If this check box is selected, the chart displays the capacity used for critical capacity requirements.
- Planned Production Orders
-
If this check box is selected, the chart displays the capacity used for planned production orders.
- Production Orders
-
If this check box is selected, the chart displays the capacity used for production orders.
- PCS Activities
-
If this check box is selected, the chart displays the capacity used for PCS activities.
- Service and Maintenance Orders
-
If this check box is selected, the chart displays the capacity used for service orders and maintenance orders.
- Graph Type
-
The type of chart to be drawn.
Note: This is only an initial setting. Once the chart is displayed, you can switch from one chart type to another.