Generate Job Shop Planning Bills of Material (cprpd3246m900)

Use this session to create the job shop bills of material data based on the data in the Generic Planning Bill of Material (cprpd3145m000) and the Generic Bill of Material (tipcf3110m000) sessions. This data is created using these two sources:
  • The Generic Bill of Material for items that are configured by PCF.
  • The Generic Planning Bill of Material for items configured by CPQ.
Note: This session can be accessed only if the Configurations by Site field is set to In Preparation in the Implemented Software Components (tccom0100s000) session.

Field Information

Generate for
From Plan Item
The From and To fields define a range of the plan items for which the job shop planning bills of material data is generated.
Based on
Supply Source

The From and To fields define a range of supply source of the plan items for which the job shop planning bill of material (BOM) must be generated.

Allowed values

Job Shop
Repetitive
Purchase
Subcontract
Distribution
Note: The job shop planning bill of material (BOM) must be generated only for the supply source Job Shop or Subcontract.
Skip Lines Expired Before
The date and time from which the bill of material lines can be skipped when generating the job shop planning bill of material.
Options
Method

Indicates the method in which the revisions are created for the job shop planning bill of material.

Allowed values

Minimal
This option creates only one revision 000001 for the last sequence that is currently effective. The input date limit (create from) becomes the effective date of this revision.
Extended
This option creates a revision for each date period from the input date. Date periods are determined based on the specified effective and expiry dates. Effective or expiry dates on the same day are considered as one revision.
Simulate
If this check box is selected, the job shop planning bills of material data is generated in simulation mode and a preview of the generated data is displayed in the report.
Process Report
If this check box is selected, the application prints a process report with the job shop planning bills of material data that is generated successfully.
Note: 
  • By default, this check box is selected.
  • This field is enabled only if the Simulate check box is cleared.
Validate and Approve
If this check box is selected, the job shop planning bill of material (BOM) is validated and is set to approved, if no errors are found.
Note: 
  • By default, this check box is cleared.
  • This field is enabled only if the Simulate check box is cleared.