Job Shop Planning List of Materials (cprpd3147m000)
Use this session to insert, update or delete Job Shop Planning list of material.
Note: This session can be accessed only if the Configurations by Site field is set to Active or Enterprise Model in Preparation in the Implemented Software Components (tccom0100s000) session.
Field Information
- Product
- The code of main item of the job shop planning list of material.
- Production Site
- The code of source site of the job shop planning list of material.
- Revision
- The revision number of the job shop planning list of material.
- Position
- The position of the job shop planning list of
material.Note: When a new material line is created, the value is updated with the next available position number.
- Sequence Number
- The sequence of the job shop planning list of
material.Note: When a new material line is created, the value is updated with the next available sequence number.
- Item
- The code of the material item.Note: The material must be the in the same Cluster as the Product.
- Planning Quantity
- The planning quantity of the material.Note: The planning quantity is rounded off based on the inventory unit of the material.
- Planning Quantity Unit
- The unit in which the Planning Quantity is expressed.
- Planning Percentage
- The percentage for which the materials must be considered.
- Warehouse
- The warehouse of the material.Note:
- The warehouse must be part of the cluster of the material.
- The warehouse must be planned by EP.
- The warehouse is default with the plan item warehouse of the material.
- Use Lead Time Offset
- If this check box is selected, the lead time offset can be specified.
- Lead Time Offset
- The period specified for the lead time
offset.Note: This field is enabled only if the Use Lead Time Offset is check box selected.
- Lead Time Offset Unit
- The unit in which Lead Time Offset is expressed. Note: This field is enabled only if theUse Lead Time Offset is check box selected.
Allowed values
- Hours
- Days
- Phantom
- If this check box is selected, the material or component is a phantom.