Planning - Generic Bill of Material (cprpd3145m000)

Use this session to to generate a generic BOM for a configurable item.

Note: 

The generic BOMs generated in this session are used only for planning purposes.

The CPQ Configurator Integration check box must be selected to use this session.

Field Information

Main Item
The plan item that the planned order produces.
Ordering Site

The site ID.

Item Type

The type of the main item.

Allowed values

item type

Supply Source

default supply source

Allowed values

Job Shop

A bill of material (BOM) and routing are available for the item. The demand is filled by a production order.

Repetitive

A list of materials and a work cell are available for the item. The demand is filled by a production schedule.

Assembly

An assembly bill of material (BOM) and assembly lines are available for the item. The demand is filled by an assembly order.

Purchase

No production data is available for item. The demand is filled by a purchase order.

Subcontract

The item is supplied by subcontracting the production process. A bill of material (BOM) is specified for this item.

Note: The Subcontracting with Material Flow check box must be selected to select this supply source.
Distribution

The item is supplied by a planned distribution order.

BOM Quantity
Position
The position number of the component.
Sequence Number
The sequence number of the component.
Item
The component item that is part of the manufactured item. The components must be items of the Purchased, Manufactured, or Product item type. The component must be defined in the Items (tcibd0501m000) session.
Note: If the main item is of the item type Tool, components with the Tool type are allowed.
Item Type
The item type.
Operation
The operation for which operation the material of the BOM line is issued to the job shop.
  • If you enter zero (0), you can use the BOM Line - Material-Routing Relationships (tibom0140m000) session to determine on which operation the material is issued.
  • If you enter a value other than zero (0), for example, 10, the material is issued at operation 10. This operation applies to all routings that are defined for the manufactured item. If the operation does not exist for the manufactured item's routing(s), the BOM line material is issued at the first operation of the routing.
Note: To avoid entering the code of a nonexistent operation, you are advised use the zoom function for this field and select an operation from the Routing Operations (tirou1102m000) session.
Warehouse
The warehouse where the component is stored and where the allocation for a production order is made.
Effective Date
The first day on which a record or a setting is valid.
Expiry Date
The date the bill of material (BOM) is no longer valid.
Planning Quantity

The planning quantity of a component in a generic bill of material is used in the Enterprise Planning calculation when determining the average requirements for this component, as a result of planned orders for generic items on a higher level in the generic product structure.

The Enterprise Planning calculation will incorporate this planning quantity (multiplied by the planning percentage) as the net requirement for the production of the generic manufactured item. The exact material requirements are not known during the Enterprise Planning calculation, because there is no customer for the generic item in this planning phase. As a result, a specific product variant has not yet been selected.

Planning Percentage
The planning percentage serves to perform a Enterprise Planning calculation, as does the Planning Quantity field.
Use Lead Time Offset
If this check box is selected, you can specify the lead-time offset.
Lead Time Offset
This field is only used by Enterprise Planning. When a generic item is planned, the start date of an operation is calculated by offsetting the requirement date of the generic item with the lead time offset. The finish date of the operation is determined by adding the planned production time. The planning percentage is used to determine the required work center capacity.
Phantom
If this check box is selected, the component item is defined as a phantom in the Item - Production (tiipd0101m000) session. You can use phantom items to record technical information about the product structure or to carry out standard cost calculations.
Note: 
  • If the component item is a phantom, you cannot define alternative materials.
  • If the Main Item is a phantom, a check mark is displayed on the header and derived from the Item - Production (tiipd0101m000) session.
  • If the Item is a phantom, the check box on the BOM line is selected.