Copy Demand, Supply or Inventory Plan (cprmp2230m000)

Use this session to copy data from one field of an item's or channel's master plan to another field. For example, you can copy the demand forecast to the extra demand field.

Field Information

Scenario

Specify the scenario for which LN must copy data between the specified fields of the item master plan and/or the channel master plan.

Note: The scenario's plan status must be Open.

Planner

Specify the range of planners that LN must take into account to select plan items of which the selected master data must be copied.

Channel

Specify the range of channels that LN must take into account to copy data between the specified fields of channel master plans.

Period

Specify the range of plan periods for which LN must copy master data between the specified source and target field.

From Plan Item

Specify the range of plan items for which LN must copy master data from the source to the target field of the item master plan and/or the channel master plan.

Source

Select the source field of which LN must copy the value to the target field.

Nullify Source

If this check box is selected, LN sets the value of the source fields to zero. You can use this option if you do not want to copy a value, but move it from one field to another.

Target

Specify the target field to which LN must copy the data of the source field.

Complete Update

If this check box is selected, LN updates the master plan of the selected plan items after the copying process.

Percentage

The percentage of the source field value that LN copies.

Example

  • If you enter 0, LN does not copy quantities.
  • If you enter 60, the quantities that LN copies are 60% of the quantities in the source scenario.
  • If you enter 110, the quantities that LN copies are 10% higher than the quantities in the source scenario.
Update Mode

The update mode determines whether LN does one of the following:

  • Select Overwrite if LN must use the data from the source scenario to overwrite the existing data in the target scenario.
  • Select Add To if LN must add the source values to the existing values.