Create Order Group for Planned Orders (cppat3250m000)
Use this session to group planned production orders in an order group.
Field Information
- Planned Order Group Series
-
The series from which the order-group number is taken.
Allowed values
Choose a series from the number group that is specified in the Number Group for Order Grouping field in the Production Order Parameters (tisfc0100s000) session.
Enterprise Planning uses the first free number from this series.
- Site
-
The code of the site.
- Actual Scenario
-
Note: You can only create planned-order groups in the actual scenario.
- Automatic Update
-
If this check box is selected, you can update the order group to include the planned orders that currently match the order group criteria.
- Order Status
-
The range of order statuses that LN must use to select planned production orders.
- Start Date
-
The range of start dates you want to use as a selection criterion.
- Finish Date
-
The range of finish dates that you want to use as a selection criterion.
- Warehouse
-
The range of warehouses that LN must use as a criterion to select planned production orders for the order group. This criterion applies to the value of the Destination Warehouse field in the Planned Orders (cprrp1100m000) session.
- Reference Operation
-
Specify the first of a range of tasks that LN must use as a criterion to select planned production orders for the order group.
For every order, LN checks whether the corresponding operations consist of tasks that are included in the task selection range you must specify here. If this is not the case, LN does not include the order in the order group.
- Task (Current)
-
Specify the last of a range of tasks that LN must use as a criterion to select planned production orders for the order group.
For every order, LN checks whether the corresponding operations consist of tasks that are included in the task selection range you must specify here. If this is not the case, LN does not include the order in the order group.
- Work Center (Current)
-
Specify the first of a range of work centers that LN must use to select planned production order for the order group.
For every order, LN checks whether the work center linked to each operation carried out to produce the concerned item, is included in the work center range you must specify here. If this is not the case, LN does not include the order in the order group.
- Work Center (Current)
-
Specify the last of a range of work centers that LN must use to select planned production order for the order group.
For every order, LN checks whether the work center linked to each operation carried out to produce the concerned item, is included in the work center range you must specify here. If this is not the case, LN does not include the order in the order group.
- Machine Type
-
Specify the first of a range of machines that LN must use as a criterion to select planned production orders for an order group.
For every order, LN checks whether the machines linked to each operation carried out to produce the concerned item, are included in the machine selection range you must specify here. If this is not the case, LN does not include the order in the order group.
- Machine
-
Specify the last of a range of machines that LN must use to select planned production orders for an order group.
For every order, LN checks whether the machines linked to each operation carried out to produce the concerned item, are included in the machine selection range you must specify here. If this is not the case, LN does not include the order in the order group.
- Routing Group
-
Specify the first of a range of routing groups that LN must use as a criterion to select planned production orders for an order group.
- Routing Group
-
Specify the last of a range of routing groups that LN must use as a criterion to select planned production orders for an order group.
- Main Item
-
If this check box is selected, you can use a range of end items as a selection criterion for the order group.
- From Main Item
-
Specify the first of a range of main items of which LN must combine the planned production orders in an order group.
- To Main Item
-
Specify the last of a range of main items of which LN must combine the planned production orders in an order group.
- Material Item Selection
-
If this check box is selected, you can use a range of component items as a selection criterion for the order group.
- From Material Item
-
Specify the first of a range of material items of which LN must combine the planned production order in an order group.
- To Material Item
-
Specify the last of a range of material items of which LN must combine the planned production order in an order group.
- Item Group
-
Specify the first of a range of item groups that LN must use as an additional criterion to select planned production orders of main items for an order group.
- Item Group
-
Specify the last of a range of item groups that LN must use as an additional criterion to select planned production orders of main items for an order group.
- Planner
-
Specify the first of a range of planners that LN must use as an additional criterion to select planned production orders of main items for an order group.
- Planner
-
Specify the last of a range of planners that LN must use as an additional criterion to select planned production orders of main items for an order group.
- Shop Floor Planner
-
Specify the first of a range of shop floor planners that LN must use as an additional criterion to select planned production orders of main items for an order group.
- Shop Floor Planner
-
Specify the last of a range of shop floor planners that LN must use as an additional criterion to select planned production orders of main items for an order group.
- Product Line
-
Specify the first of a range of product lines that LN must use as an additional criterion to select planned production orders of main items for an order group.
- Production Line
-
Specify the last of a range of product lines that LN must use as an additional criterion to select planned production orders of main items for an order group.
- Product Class
-
Specify the first of a range of product classes that LN must use as an additional criterion to select planned production orders of main items for an order group.
- Product Class
-
Specify the last of a range of product classes that LN must use as an additional criterion to select planned production orders of main items for an order group.
- Selection Code
-
Specify the first of a range of selection codes that LN must use as an additional criterion to select planned production orders of main items for an order group.
- Selection Code
-
Specify the last of a range of selection codes that LN must use as an additional criterion to select planned production orders of main items for an order group.
- Tool Kit
-
If this check box is selected, you can use a range of tool kits as a criterion to select planned production orders for the new order group.
- Tool Kit
-
Specify the first of a range of tool kits that LN must use as a criterion to select planned production orders for an order group.
- Tool Kit
-
Specify the last of a range of tool kits that LN must use as a criterion to select planned production orders for an order group.
- Tool Type
-
If this check box is selected, you can use a range of tool types as a criterion to select planned production orders for the new order group.
- From Tool Type
-
Specify the first of a range of tool types that LN must use as a criterion to select planned production orders for the new order group.
- To Tool Type
-
Specify the last of a range of tool types that LN must use as a criterion to select planned production orders for the new order group.
- Tool Serial Number
-
Specify the first of a range of tool serial numbers that LN must use as a criterion for the tool type selection range.
- Tool Serial Number
-
Specify the last of a range of tool serial numbers that LN must use as a criterion for the tool type selection range.
- Maximum Group Size
-
The maximum number of orders that LN can add to the planned-order group.
- Include Grouped Orders
-
This check box determines how LN treats orders that match the selection criteria, but which are already part of an existing order group.
If this check box is selected, and you click , the Assign Production Orders to Planned Order Group (cppat3151s000) session also displays the planned production orders that belong to another order group. However, you cannot select those planned orders for the new order group.
If this check box is cleared, the Assign Production Orders to Planned Order Group (cppat3151s000) session hides these planned orders.
- Group Description
-
Enter a description for the planned-order group.