Work Centers (cppat0211m000)
Use this session to get an overview of all the work centers that are used for the planned production order that you highlighted in the Select Order Planning for Transfer (cppat0210m000) session.
For each work center, the workload norm, the workload tolerance, and the workload are displayed.
Field Information
- Actual Scenario
-
The code of the actual scenario.
LN only displays the work centers that are used for planned orders for the actual scenario.
- Work Center
-
This field contains the various work centers used for the order you highlighted in the Select Order Planning for Transfer (cppat0210m000) session.
- Workload Norm
-
In this field, LN fills in the calculated workload norm for the corresponding work center.
The workload norm is based on the value specified in the Workload Norm field in the Work Centers - Planning (cprpd2100m000) session and the workload norm percentage that the planner specified in the Transfer Order Planning (cppat1210m000) session.
The formula to calculate the workload norm is:
Workload Norm * Workload Norm Perc.
- Workload Tolerance
-
The workload tolerance specified for the corresponding work center in the Work Centers - Planning (cprpd2100m000) session.
- Workload
-
The workload on the specified work center for the order that you highlighted in the Select Order Planning for Transfer (cppat0210m000) session.
LN calculates the workload, based on the already transferred orders and new orders.