General procedure for concept activation
Activating a concept involves these main steps:
- Set the status of the concept to In Preparation to enable the activation activities.
- Perform the activation activities.
- Set the status of the concept to Active.
Activating a concept
-
In the Concept Activation (tcemm4600m100) session, select the overall concept to be activated.
-
In the Concept Activation (tcemm4600m000) workbench session, click the appropriate concept tab.
-
Click In Preparation. You are prompted to continue or cancel.
-
Click OK to enable the activation activities.
- Perform the activation activities.
-
Click
to activate the concept. -
Repeat the procedure to activate the next concept.
Performing activation activities
-
On the appropriate concept tab of the Concept Activation (tcemm4600m000) workbench session, click an activation activity. Activation activities are presented as command buttons. For example, if you are activating the Multisite overall concept, on the Item Type Product concept tab, click .
Note:The order in which to perform the activation activities is indicated by the availability of the activity options in the Concept Activation (tcemm4600m000) workbench session.
If you click an activation activity button in the Concept Activation (tcemm4600m000) workbench session, the Activation Activity (tcemm4610m000) session starts in which the options and sessions required to complete the activity are available.
-
In the lines section of the Activation Activity (tcemm4610m000) session, select the company for which to perform the activation activity.
-
From the appropriate menu of the lines section of the session, select .
Alternatively, on appropriate menu of the header section of the session, select .
-
From the appropriate menu of the lines section of the session, start the master data or the parameter sessions in which to complete the setup for the current activation activity and specify the data and settings as required.
-
From the appropriate menu of the lines section of the session, select .
Alternatively, from the appropriate menu of the header section of the session, select .
-
If multiple companies are present, perform steps 2 - 5 for the other companies.
-
Close the Activation Activity (tcemm4610m000) session.
-
In the Concept Activation (tcemm4600m000) workbench session, click the next activation activity and repeat the procedure until all activation activities are completed.
Checking and correcting activation activities
After finishing an activation activity, you can start the Activation Activity (tcemm4610m000) session to check and correct the activity, if required. To correct an activity, select the relevant company and from the appropriate menu of the lines section, select . For steps that are performed for all companies simultaneously, from the appropriate menu of the header section of the session, select .
Until the concept is activated, you can restart an activation activity as many times as you need.