BOM (pdpdm1601m000)
Use this session to view and maintain the Bill of Material (BOM) for an item.
- The xcad fields are customized and optional. The fields can be used to specify file names or information about objects.
- You can use the option to select the BOM lines that have to be copied to another item.
- You can use the option to link or copy the selected Items or BOM lines (selected using the option) as children to the selected parent document.
The Bill of Material contains the component items of a manufactured item. Each BOM line contains information about the position of the component item in the BOM, the required quantity, and the expiry date of the component item.
Field Information
- Item
- The item code.
- Parent Revision
- The revision number of the parent item.
- Find No.
- The number that enables you to compare the Item attributes and the attributes of the linked properties.
- Component
- The code of the item component.
- Status
-
The status of the parent item.
Allowed values
- Draft
- Released
- Under Change
- Obsolete
- Status
-
The status of the child item.
Allowed values
- Draft
- Released
- Under Change
- Life Cycle
-
The stage at which the parent item is, in the production life cycle. This is used to track the item through the various phases (from design to production).
Allowed values
- In Design
- Approved to Production
- Released to Production
- Life Cycle
-
The stage at which the child item is, in the production life cycle. This is used to track the item through the various phases (from design to production).
Allowed values
- In Design
- Approved to Production
- Released to Production
- Created By
- The name of the user who creates the parent BOM.
- Created By
- The name of the user who creates the child BOM.
- Created On
- The date and time when BOM is created.
- Quantity
-
- Scrap Quantity
- The item quantity that is considered as scrap.
- Scrap Percentage
- The percentage of the item value that is considered as scrap.
- Unit of Measure
- The unit of measure used for the item.
- Length
- The length of the item.
- Width
- The width of the item.
- Number of Units
- The number of units of the item.
- Disposition
- The attribute is used as a comment field to store data relating to placement of the component in the assembly.
- Default Template
- The code of the template defined for the
item.Note: The value is defaulted from the BOM Defaults (pdadm5153m000) session.
- Miscellaneous
-
- Standard Configuration
-
If this check box is selected, the item is produced with a standard configuration.
- Phantom
-
If this check box is selected, the item is a phantom item.
- As Required
-
If this check box is selected, the item is a phantom item.
- Alternatives Present
-
Indicates if alternative item are available for the BOM lines.
- Reference Designators Present
-
Indicates if reference designator is available for the BOM lines.
- Text
- Indicates if the BOM text is defined for the BOM line.
- Effective From
- The date from which the effectivity of the BOM is applicable.
- Effective To
- The date up to which the effectivity of the BOM is applicable. The application sets the date when a new revision of the item is released.
- Created By
- The name of the user who creates the BOM.
- Created On
- The date and time when BOM is created.
- CAD Instance Name
- The name of the variant in the CAD family.
- Position
- The position of the component item in the BOM.
- Company
- The ERP company used for comparison.
- Project (PCS)
- The ERP PCS Project (if applicable) used for comparison.
- Additional Information
- The additional information related to BOM.
- Originating App
- The application using which the BOM is created.
- Input/Output
-
Indicates if the item is of input or output.
Allowed values
- Input
- Output
- Material Relation
-
The material relationship with the BOM.
Allowed values
- Primary Product
- Co Product
- By Product
- Waste Product
- Active Ingredient
- Inactive Ingredient
- Primary Ingredient
- Formula Based
- Catalyst
- Recoverable
- Material Percent
- The percentage of material.
- Scaling
-
The type of scaling.
Allowed values
- Batch
- Order
- Unit
- Child Unit
- Indicates the child unit.
- Reference Material
-
Indicates if any reference materials available for the item.
- Exception Present
-
Indicates if the exception is specified for the item.
- Operation
- The action to be performed on the selected field or column.
- Work Center
- The code of the work center.
- Note Fn1
- The additional information related to item.
- Note Fn2
- The additional information related to item.
- Note Fn3
- The additional information related to item.
- Note Fn4
- The additional information related to item.
- Note Fn5
- The additional information related to item.
- Size Unit
- The additional information related to item.
- Skip to Production
- If this check box is selected, the item skips to production.
- xcad1
- The file name (used to replace references correctly in the assemblies) or collaboration information about objects.
- xcad2
- The file name (used to replace references correctly in the assemblies) or collaboration information about objects.
- xcad3
- The file name (used to replace references correctly in the assemblies) or collaboration information about objects.
- xcad4
- The file name (used to replace references correctly in the assemblies) or collaboration information about objects.
- xcad5
- The file name (used to replace references correctly in the assemblies) or collaboration information about objects.
- Originating App
-
The application using which the BOM is created.
Allowed values
- ECM
- MSProject
- IMAN
- UG Manager
- Inventor
- ME10
- Altium
- DraftSight
- Jvue Markup
- SolidWorks
- ERP
- AutoCAD
- SolidEdge
- ProE
- Ug
- PLM
- MSOffice
- CatiaV5
- CatiaV4
- E-Source
- Lotus Notes
- CRM
- MSWord
- MSExcel
- MSPowerPoint
- MSOutlook
- Approval Date
- The date on which the BOM is released.
- PLM Project
- The PLM project for which the BOM is created.
- Security Access Level
-
The level of security access provided to the user.
Allowed values
- Unrestricted
- Restricted
- Confidential
- Secret
- Top Secret
- Created By
- The name of the user who creates the BOM.
- Item Type
-
The item type used for the project.
Allowed values
- Purchased
- Engineering Module
- Manufactured
- Product
- Generic
- Created On
- The date and time when BOM is created.
- Previous Revision
- The alpha numeric code of the existing revision of the document.
- Derived From
- The original item from which this item is copied.
- The original item revision from which this file is derived.
- Category
- The code of the item category.
- The name of the item category.
- Business Process
- The business process for which the item is required.
- Modification
- The code of the modification.
- Standard
- The standard of the item.
- Serialized
-
If this check box is selected, the item is serialized.
- Lot Control
- If this check box is selected, the item is lot controlled.
- End Item
- If this check box is selected, the item is an End item.
- Cost
- The cost of the item.
- Currency
- The currency in which the item cost is specified.
- Obsolete
-
Indicates that the item is no longer in use.
- Estimated Weight
- The estimated weight of the manufactured item.
- Customizable
-
Indicates if the item is customized.
Allowed values
- make-to-order
- anonymous item
- Size
- The default size of the item.
- Material
- The material from which the item is manufactured.
- Object Type
-
The category of the object.
Allowed values
- Item
- Folder
- Maintenance Sales Order
- Maintenance Sales Order Item Lines
- Bill of Material
- Contracts
- Inspection Plans
- Inspection Plan Characteristics
- Serial End Item Header
- Serial End Item Components
- Opportunity
- Warehouse Order
- Business Process
- Planned Order
- Purchase Requisition Order
- Incident Number CAR
- Incident Number CAR1
- Incident Number CAR2
- Incident Number CAR3
- CUSAI Number
- Planned Item
- ERP Work Center
- Instruments
- Tool
- Installation
- Adjustment Order
- Adjustment Order Line
- Warehouse Receipt
- Match Approve Pur Inv
- Manufacturer
- Supplier
- Contractor
- Category
- File
- Hardcopy
- Business Process Comment
- ECM File
- ECM Document
- Purchase Order
- Purchase Order Line
- Sales Order
- Sales Order Line
- Production Order
- Service Order
- Routing
- Routing Line
- Fixed Asset
- Sales Quotation
- Sales Quotation Line
- Purchase Inquiry
- Purchase Inquiry Line
- ECM Project
- Charge Element
- Employee
- Business Partner
- Customer BP
- Supplier BP
- LOT
- Abstract Items
- Configuration Items
- Service Order Activity
- Project (TP)
- Project (PCS)
- E Item
- P Item
- Service Installation
- Installation Component
- Customize Routing
- Customize Routing Line
- ERP Task
- Generic
- ERP Machine
- Customized Item
- Service Call
- Service Contract
- Service Contract Quote
- Service Order Quote
- Service Quote Activity
- Reference Activity
- ECO
- Budget
- Feature
- Calculation Part
- Routing Sheet Budget
- Routing Sheet Operation
- Sales Activity
- Purchase Requisition
- Purchase Req Line
- SCH Sales Contract
- SCH Sales Contract Line
- SCH Purchase Contract
- SCH Purchase Cont Line
- Option
- NCR
- Abstract File
- Abstract Document
- Abstract BP
- Illustration
- Material
- Formula
- Markup
- Tessellation
- Plan Material Purchase Order
- Project Activity
- Labor Budget
- Equipment Budget
- Subcont Budget
- Sundry Budget
- Purchase Advice
- Purchase Advice Line
- Material Requisition
- Work Breakdown Structure
- System
- Document
- System Part
- Space
- Received Invoices
- Received Pur Invoices
- Received Pur Inv Line
- Serialized Items
- Serial Numbers
- Physical Breakdowns
- Work Order
- Work Order Activities
- Activity/Element
- The default code of the project element / activity linked to the item.
- Long Lead Item
-
If this check box is selected, the item is the long lead item.