Examples of subcontracting rates
The following data is used in the examples:
| Subcontracting rate | $50 |
| Subcontracting factor | 1.0 |
| Gross output | 170 |
| Man hours run | Gross output * cycle time (hrs) = 170 * 0.1 = 17 |
| Machine hours run | Gross output * cycle time (hrs) = 170 * 0.1 = 17 |
| Man hours setup | Setup time (hrs) = 2 |
| Machine hours setup | Setup time (hrs) = 2 |
Unit
Subcontracting costs =
gross output * subcontracting rate= 170 * 50 = $8,500
Operation rate
Only applicable if the Werkstattfertigung nach Standort parameter in the Implementierte Software-Komponenten (tccom0100s000) session is set to Nicht aktiv or In Vorbereitung.
Subcontracting costs =
gross output * subcontracting rate * rate factor= 170 * 50 * 1.0 = $8.500
Man hour rate
Only applicable if the Werkstattfertigung nach Standort parameter in the Implementierte Software-Komponenten (tccom0100s000) session is set to Nicht aktiv or In Vorbereitung.
Subcontracting costs =
(man hours setup + man hours run) * subcontracting rate= (2 + 17) * 50 = $950
Machine hour rate
Only applicable if the Werkstattfertigung nach Standort parameter in the Implementierte Software-Komponenten (tccom0100s000) session is set to Nicht aktiv or In Vorbereitung.
Subcontracting costs =
(machine hour setup + machine hours run) * subcontracting rate= (2 + 17) * 50 = $950
Hour
Only applicable if the Werkstattfertigung nach Standort parameter in the Konzeptaktivierung (tcemm4600m000) session is set to Aktiv.
Subcontracting costs =
(machine hour setup + machine hours run) * subcontracting rate= (2 + 17) * 50 = $950