Operation subcontracting without material flow support
The simplest way of subcontracting in LN is to create a subcontracting purchase order to record the operations that are outsourced to a subcontractor. This means that you purchase labor from a subcontractor. For this type of subcontracting, no material is supplied to the subcontractor.
To start a subcontracting process without material supply, you must set up the following data:
-
Fremdvergebene Dienstleistung item
In the Artikel (tcibd0501m000) session, define an item with item type Fremdvergebene Dienstleistung. This is an administrative item that represents the subcontracted work. The Fremdvergebene Dienstleistung item is displayed on the subcontracting purchase order. -
Subcontracting work center
Define a subcontracting work center in the Abteilungen (tirou0101m000) session. In the Arbeitsgänge (tirou1102m000) session, link the subcontracting work center to the routing operation that you want to subcontract. -
Subcontracting rates
In the Fremdbearbeitungskostensätze (ticpr1160m000) session, define the subcontracting costs. In the Unterbaugruppe field you must enter the Fremdvergebene Dienstleistung item. Note that you must define the rate for the correct combination of price calculation code and subcontractor. If you want to define an item-specific subcontracting rate, fill the Übergeordneter Artikel field.
Only applicable if the Werkstattfertigung nach Standort parameter has the status Nicht aktiv in the Implementierte Software-Komponenten (tccom0100s000) session.
Ad hoc subcontracting
If you had not planned to subcontract one or more operations, and consequently no subcontracting work centers are defined in the routing, use the Arbeitsgänge fremdvergeben (tisfc2210m000) session to replace an existing work center with a subcontracting work center on the operations that you want to subcontract.