Assigned Activities - Gantt

This Assigned Activities section displays a graphical view of the activities of selected origins based on the planned start and finish time of the assignment. The user can view all the employees in the left panel and the activities assigned to the employees (assignments) in the right panel. The employee’s availability and non-availability, based on the calendar data, is also displayed. The first and second row of the Gantt chart display the activity constraints of a selected activity, including the planned Start/Finish Time, Earliest Start/Latest Finish Time, the calendar assigned to the Installation Group, and so on.