Activity Set for Planned Activities (tsspc3610m200)
Use this session to view the details of activity set lines for planned activities.
Field Information
- Group
 - 
            
The unique ID of the group.
 - Allocated Resource
 - 
            
The assigned resource of the specified group planning.
 - Search Argument
 - Activity Set
 - 
            
The group planning activity set number.
 - Activity Set Sequence
 - 
            
The sequence number of the group planning activity set.
 - Sort Method
 - 
            
The sorting method for planned activities in an activity set.
Allowed values
- Earliest Start
 - Latest Finish
 - Latest Start
 - Planned Start
 - Planned Finish
 
 - Frozen
 - 
            
If this check box is selected, you cannot add new groups to the existing groups.
 - Firm Planned
 - 
            
If this check box is selected, the group is firm planned. That is, you cannot change the start and finish date of the group.
 - Keep Sequence of Activities
 - 
            
If this check box is selected, LN does not change the sequence of the activities when the specified group is planned.
 - Original Group
 - 
            
The planning group number from which the activity sets are originating.
 - Original Activity Set
 - 
            
The planning activity set number from which the activity sets are originating.
 - Search Argument
 - Planned Start Time
 - 
            
The start date and time of the first activity sets in the specified group.
 - Planned Finish Time
 - 
            
The finish date and time of the last activity sets in the specified group.
 - Total Activity Duration
 - 
            
The cumulative activity duration of activity sets in the group.
 - Time Duration Unit
 - 
            
The unit in which the total activity duration is expressed.