Activity Sets for Work Orders (tsspc3110m100)
Use this session to view and maintain group planning groups generated from group planning activity sets for work orders.
Field Information
- Group
 - 
            
The unique ID of the group.
 - Allocated Resource
 - 
            
The department assigned to the specified group. Assigned department are copied from group planning to the work order activity.
 - Keep Sequence of Activities
 - 
            
If this check box is selected, LN does not change the sequence of the activities when the specified activity set is planned.
 - Start Date Activity Sets
 - 
            
The start date of the activity set. LN displays the activity sets with a start date later than the specified date.
 - Finish Date Activity Sets
 - 
            
The finish date of the activity set. LN displays the activity sets with a finish date earlier than the specified date.
 - Moved Activity Sets
 - 
            
If this check box is selected, LN displays the activity sets that have been moved from another group.
 - Activity Set
 - 
            
The group planning activity set number for the activity set .
 - Planning Sequence
 - 
            
The planning sequence of the activity set .
 - Firm Planned
 - 
            
If this check box is selected, the activity set is firm planned and you cannot change the start and finish date of the activity set.
 - Frozen
 - 
            
If this check box is selected, the activity set is frozen and you cannot add new activities to the existing activity sets.
 - Planned Start Time
 - 
            
The start date and time of the first activity in the specified activity set.
 - Planned Finish Time
 - 
            
The finish date and time of the last activity in the specified activity set .
 - Sort Method
 - 
            
The sorting method for service order activities in an activity set.
Allowed values
- Earliest Start
 - Latest Finish
 - Latest Start
 - Planned Start
 - Planned Finish
 
 - Total Activity Duration
 - 
            
The cumulative duration of travel for all the activities in the activity set .
 - Original Group
 - 
            
The original planning group number.
 - Original Activity Set
 - 
            
The original activity set number.