Performance measurement

The performance measurement data enables you to track the progress and monitor the performance of a project. You can also plan for a project based on this data.

Infor LN allows you to generate and maintain the performance measurement data for a project based on these four levels:

  • Activity
  • Organizational Breakdown Structure (OBS)
  • Activity/Cost Type
  • OBS/Cost Type
Note: You can measure the performance of the project based on OBS or OBS/cost type only if the Use OBS check box is selected in the Project (tppdm6600m400) session.

You can use these sessions to add and maintain the performance measurement data for project:

  • Performance Measurement OBS (tpppc5560m000)
  • Performance Measurement Activity (tpppc5540m000)
  • Performance Measurement Activity/Cost Type (tpppc5541m000)
  • Performance Measurement OBS/Cost Type (tpppc5561m000)