Budgeted Extension Costs by Sundry Cost Control Code (tpptc3539m000)
Use this session to list budgeted extensions by sundry cost control code for:
- The selected project code
 - The extension code
 - The cost analysis version
 
Field Information
- Project
 - 
            
The code that uniquely identifies the project.
 - Project Status
 - 
            
The project's status.
 - Budget Cost Analysis Version
 - 
            
The code that uniquely identifies the cost analysis.
 - Last Calculation Time
 - 
            
The date on which the latest budget-cost analysis was performed via the Generate Budget Cost Analysis (tpptc3200m000) session for the selected budget-cost analysis code.
 - Extension
 - 
            
The code that uniquely identifies the extension.
 - Currency
 - 
            
The default currency in the overview session is the project currency. Both in a dependent and in an independent currency system you can change this currency to other currencies with the Rotate Currency option <CTRL-R>.
. The following sequence is applicable:
- Project currency
 - Local currency
 - Reporting currency 1
 - Reporting currency 2
 
Note: Only the last three currencies are home currencies. - Control Code Sundry Cost
 - 
            
The code that uniquely identifies the control code.
 - Reference Type
 - 
            
The nature of the control code.
 - Sundry Cost Amount
 - 
            
The total budgeted cost of the extension for the control code (excluding surcharges).
 - Surcharge Amount
 - 
            
The amount originating from surcharges which are controlled via the control code.