Control Data (Equipment Lines) (tpptc1537m000)
Use this session to view the generated budget lines of the cost-type equipment. Separate lines are generated for internal vs external equipment.
Field Information
- Project
 - 
            
The code that identifies the project.
 - Description
 - 
            
The description or name of the code.
 - Project Status
 - 
            
The project status.
 - Equipment
 - 
            
The code that identifies the equipment.
 - Services Trade
 - 
                  
The code of the Services Trade used to categorize cost objects and to match the Buy-from Business Partner (supplier) during the requirements planning.
Note:- This field is displayed only if the Services Procurement is set to In Preparation or Active in the Implemented Software Components (tccom0100s000) session.
 - You must specify this value if the Procurement by field is set to Equipment Procurement Order.
 - The combination of Services Trade and Buy-from Business Partner must be valid.
 
- Must exist in the Services Trades (tcmcs2113m000) session.
 - Must have the Nature of Supply Type set to Equipment.
 
 - Equipment Quantity
 - 
                  
The equipment quantity.
Note:- This field is enabled only if the Cost type is set to Equipment.
 - This field is displayed only if the Services Procurement field is set to Active or In Preparation in the Implemented Software Components (tccom0100s000) session.
 - This value must be specified if the Services Procurement field is set to Active in the Implemented Software Components (tccom0100s000) session.
 
 - Cost Determination
 - 
                  
Indicates how cost amounts related to the cost object are calculated in the actual budget.
Allowed values
- Quantity
 - 
               
The costs related to the subcontracting cost object are calculated, by quantity-based measure of productivity.
 - Amount of Time
 - 
               
The costs related to the subcontracting cost object are calculated, by time-based measure of productivity. Example, the subcontractor can be paid by the hour.
 - Rate Only
 - 
               
The costs related to the subcontracting cost object are calculated, based on only an agreed rate.
 - Amount Only
 - 
               
The costs related to the subcontracting cost object are calculated, based on only an amount (lump sum).
 
Note: The field can be set to Rate Only or Amount Only only if:- The Services Procurement is set to In Preparation or Active in the Implemented Software Components (tccom0100s000) session.
 - The Procurement by field is set to Subcontracting Procurement Order.
 
 - Description
 - 
            
The description or name of the code.
 - Sequence Number
 - 
            
The sequence number.
 - Amount of Time
 - 
            
The duration of the equipment's usage, expressed in the time unit.
 - Time Unit
 - 
            
The time unit.
 - Unit Cost
 - The standard cost of the equipment.Note: This value can be specified only for the equipment with the cost determination method set to Rate Only.
 - Currency
 - 
            
The home currency for the cost amount.
 - Cost Amount
 - 
            
The total cost of the budget line in the control data.
 - Cost Amount [%s]
 - 
            
The amount in the home currency.
 - Plan
 - 
            
The code that uniquely identifies the plan.
 - Activity
 - 
            
The code that identifies the activity.
 - Description
 - 
            
The description or name of the code.
 - Budget Status
 - 
            
The budget status of the activity.
 - Cost Component
 - 
            
The code that identifies the cost component.
Note: You can only specify a cost component for which the Component Type is set to Detail or Collect in the Cost Components (tcmcs0148m000) session. - Control Code
 - 
            
The code that identifies the control code.
 - Extension
 - 
            
The code that identifies the extension.
 - Description
 - 
            
The description or name of the code.
 - Extension Status
 - 
            
The status of the extension.
 - Element
 - 
            
The code that identifies the element.
 - Procurement by
 - 
                  
The default option to indicate the type of procurement order that is generated for the cost object.
Allowed values
- Purchase Order
 - Subcontracting Procurement Order
 - Equipment Procurement Order
 
Note:- This field is displayed only if the Services Procurement is set toIn Preparation or Active in the Implemented Software Components (tccom0100s000) session.
 - This field cannot be set to Purchase Order if the Cost Determination field is set to Amount Only or Rate Only.
 
 - Description
 - 
            
The description or name of the code.
 - Budget Status
 - 
            
The budget status of the element.
 - Budget Line Number
 - 
                  
The sequence number of the element or activity budget line for which the control data is generated.
Note: This field is used only if the Combine Requirements Planning On is set to Budget Line Level in the Project (tppdm6600m400) session.