Element Budget Structure (tpptc1509m000)
Use this session to list the multilevel tree structure of the element budget.
Field Information
- Project
 - 
            
The code that uniquely identifies the project.
 - Project Status
 - 
            
The project's status.
 - User
 - 
            
Logon code.
 - Level No.
 - 
            
The level of the element in the tree structure.
 - Sequence Number
 - 
            
The code and description of the elements in the element budget structure. The indentation indicates each element's relative position.
 - Progress
 - 
            
If this check box is selected, you maintain the progress for the selected element. If this check box is cleared, you maintain the progress for an element at a lower level in the budget structure.
 - Cost Control
 - 
            
If this check box is selected, you control the costs for the element. If this check box is cleared, you do not control the costs for the element.
 - Invoice
 - 
            
This indicates whether the element may be invoiced.