Budget Cost Surcharge History by Project (tpptc0535m000)
Use this session to display the cost surcharge history for surcharges that are based on all the budget lines of the selected project.
The surcharge changes are shown only if the Log History of Budget check box is selected in the Project Budget Parameters (tpptc0100s000) session.
Field Information
- Project
-
The code that identifies the project.
- Project Status
-
The project's status.
- General
-
- Sundry Cost
-
The code that uniquely identifies the sundry cost.
- Sequence Number
-
The code that uniquely identifies the sequence number.
- Percentage
-
The surcharge percentage.
- Purch. Price Trans. Date
-
The date on which the surcharge transaction was performed.
- Transaction Type
-
Indicates the action performed on the surcharge transaction.
Allowed values
- Add
- Modify
- Delete
- User
-
The user's login code.
- Element
-
The code that uniquely identifies the element.
- Plan
-
The code that uniquely identifies the plan.
- Activity
-
The code that uniquely identifies the activity.
- Cost Component
-
The code that uniquely identifies the cost component.
Note: You can only specify a cost component for which the Component Type is set to Detail or Collect in the Cost Components (tcmcs0148m000) session. - Extension
-
The code that uniquely identifies the extension.
- Effectivity
-
- Status
-
The status of the budget.
Allowed values
- Free
-
The data can be modified.
- Actual
-
The data other than the total contract amount, management reserve, and the profit fee, can be modified.
- Final
-
The amounts per activity or cost type in the Top Down Budget Data (tpptc5110s000) session cannot be modified.
- Effective Date
-
The date on which the surcharge takes effect. This date is compared with the project start date in order to define whether the surcharge applies or not.
- Expiry Date
-
The date on which the surcharge expires. This date is compared with the project start date in order to define whether the surcharge applies or not.