Planned Equipment Requests (tppss6125m000)
Field Information
- Project
 - 
            
The unique code that identifies the project.
 - Description
 - 
            
The name of the equipment.
 - Project Status
 - 
            
The current project status.
Allowed values
- Free
 - Active
 - Finished
 - Closed
 - Archived
 
 - Planned Equipment Request
 - 
            
The unique code that identifies the planned equipment request.
 - Series Description
 - 
            
The description or name of the code.
 - Equipment
 - 
            
The equipment code.
 - Reference Type
 - 
            
The reference type for the planned equipment request.
Allowed values
- Project
 - 
               
Specific to the selected project.
 - Standard
 - 
               
Common to all projects.
 
 - Description
 - 
            
The description or name of the code.
 - Serial Number
 - 
            
The serial number of the equipment. The serialized item defaults from Service.
 - Quantity
 - 
            
The quantity of the equipment.
 - Unit
 - 
            
The unit in which the quantity is measured.
 - Amount of Time
 - 
            
The amount of time for which the equipment request is created.
 - Time Unit
 - 
            
The unit in which the amount of time is expressed.
 - Ship-to Address
 - 
            
The address to which the equipment must be shipped. The address is defaulted from activity or project.
 - Name
 - 
            
The address details.
 - Request Status
 - 
            
The planned equipment request status.
Allowed values
- Planned
 - 
               
The order can be either inserted manually or generated automatically. It will be replaced by the next generation run.
 - Firm-Planned
 - 
               
The order cannot be changed or deleted by a subsequent generation run. It can however be manually changed.
 - Approved
 - 
               
The order is protected from manual changes and also from the next generation run. Additionally, it can be transferred.
 - Transferred
 - 
               
The planned purchase order can be handed over to a purchase order in Procurement .
 - Canceled
 - 
               
The order is set to be deleted in the next generation run. (If the run is executed, this order is deleted unless you revise your decision).
 
 - Operated Equipment
 - 
            
If this check box is selected, the equipment is allocated with an assigned employee to operate the same.
 - Cost Rate
 - 
            
The currency in which the equipment cost is expressed.
 - Cost Rate
 - 
            
The cost rate of the equipment.
 - Image
 - 
            
The image of the equipment is displayed, if present.
 - Element
 - 
            
The code that identifies the element.
 - Description
 - 
            
The description or name of the code.
 - Work Authorization Status
 - 
            
The work authorization status of the element.
Allowed values
- Free
 - On Hold
 - Released
 - Finished
 - Closed
 
 - Activity
 - 
            
The code that identifies the activity.
 - Description
 - 
            
The description or name of the code.
 - Work Authorization Status
 - 
            
The work authorization status of the activity.
Allowed values
- Free
 - On Hold
 - Released
 - Finished
 - Closed
 
 - Cost Component
 - 
            
The cost component associated with the equipment. This is informational only.
 - Description
 - 
            
The description or name of the code.
 - Budget Line Number
 - 
                  
The cost component associated with the equipment. This is informational only.
 - Text
 - 
            
The text related to the rental equipment request. This can be instrumental in defining aspects of the equipment like condition or additional needs.
 - Planned Request Date
 - 
            
The date on which the equipment request is created.
 - On Hire Date
 - 
            
The date on which the equipment is hired.
 - Expected Off Hire Date
 - 
            
The date on which the hired equipment must expire.
 - Transaction Date
 - 
            
The date is set at the latest change to the planned equipment request.
 - Requester
 - 
            
The code of the employee who creates the equipment request.
 - 
            
The name of the employee who creates the equipment request.
 - Planner
 - 
            
The planner.
 - Name
 - 
            
The name of the planner.
 - Service Office
 - 
            
The code of the service office. The value in this field is defaulted from the Service Office specified in the Item - Service (tsmdm2600m000) session.
 - Description
 - 
            
The description or name of the code.
 - Used as a Parent Request
 - 
            
Indicates if this request is used as parent request. This is required if another request has been linked using the child request option or a dependency is present for the request.
 - Child of Request
 - 
            
The dependent equipment request of another planned equipment request. . For example, a supporting piece of equipment like a bucket to be provided together with an excavator.
 - Description
 - 
            
The description or name of the code.