Rescheduling Messages for Material (tppss6105s000)
Use this session to view the details of a rescheduling message for a material project order generated during the last PRP run.
Rescheduling messages are generated for these PRP orders:
- PRP Purchase Order
- PRP Warehouse Order
- Request for Quotation
- Purchase Order Advice
- Purchase Order
- Purchase Schedule
- Warehouse Transfer
Rescheduling messages are not generated for transferred purchase budget lines.
Field Information
- Project
-
The code that uniquely identifies the project.
- Order Type
-
The order type to which the rescheduling message applies.
This field can have the following values:
- PRP Purchase Order for the Firm-planned or Confirmed status.
- PRP Warehouse Order for the Firm-planned or Confirmed status.
- Request for Quotation for transferred PRP Purchase Orders.
- Purchase Order Advice for transferred PRP Purchase Orders that still need to be commingled and approved in Procurement.
- Purchase Schedule for transferred PRP Purchase Orders.
- Purchase Order for transferred PRP Purchase Orders.
- Warehouse Transfer for transferred PRP Warehouse Orders.
- Order Number
-
The code of the order to which this message applies.
- Position Number
-
The position number of the order line. As an order can have multiple order lines, this number is used to identify the particular line to which the rescheduling message applies.
- Sequence Number
-
The sequence number which identifies the rescheduling message.
- Item
-
The code that uniquely identifies the ordered item.
If the first segment is filled, the item is a project-specific cost object. If it is empty, then the item is a standard cost object.
- Effectivity Unit
-
The effectivity unit code. This is a display field.
- Description
-
The description or name of the code.
- Transaction Date
-
The date and time when the rescheduling message was generated.
- Quantity
-
The required quantity based on the project control budget.
- Quantity
-
The ordered quantity.
- Delivery Date
-
The required delivery date of the material. This date is calculated from the project control budget data.
- Delivery Date
-
The planned delivery date of the ordered material.
- Message
-
The type of rescheduling message.