Delete Milestones (tppss2204m000)

Use this session to delete a selected range of milestones.

Select the appropriate check boxes to delete the budget or baseline data.

If you want to delete a milestone:

  • The project status must be Free or Active
  • The status of the linked activity must be Free

Field Information

Project

The code that uniquely identifies the project of which you want to delete milestones.

Plan

The code that uniquely identifies the plan of which you want to delete milestones.

Milestone

The From and To fields define a range of: milestones you want to delete.

Activity Selection

The From and To fields define a range of: milestones you want to delete.

Activity Relationships

If this check box is selected, the activity relationships linked to the milestone are deleted.

Earned Value Method Related Data

If this check box is selected, the earned value related data from the milestone is deleted.

Baseline Data

If this check box is selected, the baseline data is deleted.

If this check box is cleared, the milestone (where it occurs in an approved baseline) is not deleted.