Delete Milestones (tppss2204m000)
Use this session to delete a selected range of milestones.
Select the appropriate check boxes to delete the budget or baseline data.
If you want to delete a milestone:
- The project status must be Free or Active
- The status of the linked activity must be Free
Field Information
- Project
-
The code that uniquely identifies the project of which you want to delete milestones.
- Plan
-
The code that uniquely identifies the plan of which you want to delete milestones.
- Milestone
-
The From and To fields define a range of: milestones you want to delete.
- Activity Selection
-
The From and To fields define a range of: milestones you want to delete.
- Activity Relationships
-
If this check box is selected, the activity relationships linked to the milestone are deleted.
- Earned Value Method Related Data
-
If this check box is selected, the earned value related data from the milestone is deleted.
- Baseline Data
-
If this check box is selected, the baseline data is deleted.
If this check box is cleared, the milestone (where it occurs in an approved baseline) is not deleted.