Copy Activities (tppss2201m000)
Use this session to copy an activity from a source to a target structure. The target can be the same plan or a different plan. The session can also be used to copy activities across projects.
- If the target is the same plan you must define the source and the target.
 - If the target is a different plan you define the source, select the Copy Across Plan check box and define the target.
 - If the target is a different project, select the Copy Across Project check box and define the target project.
 
- If you want to copy all the activities of a plan, it is easier to copy the entire plan using the Copy Plans (tppss0211m000) session. This session can also be useful for doing simulations.
 - If a material budget line is copied for which a configured generic item is present, the product variant cannot be copied.
 - For PCS items, the product variant is copied only if the budget line is copied within the same project.
 
If the budget line with a PCS item is copied to another project, the PCS item cannot be copied and must be replaced:
- If the item originates from a configured generic item, the generic item will replace the PCS item in the new project. The item that replaces the PCS item must be present in the Items - Project (tppdm0505m000) session, otherwise the budget line cannot be copied.
 - If the item is derived from a standard item, the standard item will replace the PCS item in the new project. The item that replaces the PCS item must be present in the Items - Project (tppdm0505m000) session, otherwise the budget line cannot be copied.
 - If the item is not derived from a standard or configured item, the budget line is not copied.
 
Field Information
- Action
 - 
            
- Copy Across Project
 - 
                     
If this check box is selected, the session copies the activites across projects. The Copy Across Plan check box gets checked automatically.
 - Copy Across Plan
 - 
                     
If this check box is selected, the session copies activities across plans.
Note: The check box gets checked automatically when the Copy Across Project check box is selected. - Copy Budget Data
 - 
                     
If this check box is selected, the session will copy the budget data.
The budget data can include:
- The budget lines of the activity budget or
 - The time-phased budget data (when the target is the active plan)
 
 - Copy Activity Relationships
 - 
                     
If this check box is selected, the activity relationship is also copied.
 - Copy Dates
 - 
                     
If this check box is selected, LN copies the dates depending on the value of the Date Selection field.
 
 - Date Details
 - 
            
- Date Selection
 - 
                     
Select the dates of the activity you want to copy.
You have the following options:
- 
                           
Source Dates
Use this option to copy the dates from source activity. The dates are rolled up in the target plan. - 
                           
Parent Dates
Use this option to use the dates of the parent target activity. - 
                           
Planned Date
Use this option to use the date specified in the Start Date field. 
 - 
                           
 - Start Date
 - 
                     
Specify the start date of the target activity.
 
 - Source
 - 
            
- Project
 - 
                     
The code that uniquely identifies the project from which you want to copy the activity.
 - Plan
 - 
                     
The code that uniquely identifies the plan from which you want to copy the activity.
 - Activity
 - 
                     
The code that uniquely identifies the activity that you want to copy. The structure under the activity also gets copied.
 - Project Location
 - 
                     
The location of the project from which you want to copy.
 - Activity Manager
 - 
                     
The activity manager associated with the project activity.
Note:- If this value is not specified, Infor LN considers the activity manager specified for the source project activity.
 - The specified employee must be defined in the Employees - General (tccom0101m000) session.
 - Infor LN checks the employment status based on the Last Date of Employment specified in the Employees - People (bpmdm0101m000) session. If the employee is currently not employed, Infor LN displays a notification message. However, you can continue by adding the employee as the activity manager.
 - If this value is not specified, Infor LN copies the activity manager from the project activity being copied from, only when the activity manager is an employee.
 
 - Description
 - 
                     
The description or name of the code.
 - Version
 - 
                     
The version of the time-phased budget from which you want to copy.
 
 - Target
 - 
            
- New Activity
 - 
                     
The code that uniquely identifies the activity that you want to copy the data to.
 - Parent Activity
 - 
                     
The element in the activity structure that encompasses the activity to which you want to copy.
 - Project Location
 - 
                     
The location of the project to which you want to copy the activity.
 - Plan
 - 
                     
The code that uniquely identifies the plan to which you want to copy the activity.
 - Version
 - 
                     
The version of the time-phased budget to which you want to copy the activity.
 - Create new activities with incremental code
 - 
                     
If this check box is selected, and the target activity has same code as the source activity, a new activity with an incremental code is created.
If this check box is cleared, the copying process stops and a report is generated stating that the activity with the same code is already present.
Note: The check box is available only if the Copy Across Project or the Copy Across Plan check box is selected. 
 - Conversion Factors
 - 
            
The conversion factor for the item.
Allowed values
- 
                  
Yes
LN copies the conversion factors to the target item, and approves them directly. - 
                  
No
LN copies the conversion factors to the target item. However, you must use the Conversion Factors (tcibd0103m000) session, to approve the conversion factors manually. - 
                  
Not Applicable
LN copies the conversion factors to the target item. The approved conversion factors remain approved, and the unapproved conversion factors remain unapproved. 
 -